FY2026 GAA: ₱6.79T
PisoScan

Project 18CL0050

DPWH infrastructure contract
Contract ID:
18CL0050
Fingerprint:
c7947e4adb6223…7bcebdcca0 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 12, 2018 (8 yrs 8 mo ago) · Target/actual end Jun 28, 2018
Description:
RAISING OF GRADE ALONG PAITE- MACULCOL DIKE, SAN FELIPE SIDE, SAN FELIPE, ZAMBALES
Category:
Flood Control and Drainage
Implementing office:
DPWH Zambales 1st DEO · Region III
Contractor:
ROMA CONSTRUCTION & DEVELOPMENT CORPORATION · DPWH contractor code 6514
Contract amount:
₱18,829,844.71 (₱18.8M)
Funding source:
Regular Infra - GAA 2018 OO-2
Budget year:
2018

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25CL0256Jul 18, 2025CONSTRUCTION OF FLOOD CONTROL RIVERBANK STRUCTURE ALONG SANTO TOMAS RIVER (OMAYA-BALINGCAGUING-PAITE SECTION), SAN NARCISO, ZAMBALES (PHASE 1)On-Going₱48.8M
25CL0257Jul 18, 2025CONSTRUCTION OF FLOOD CONTROL RIVERBANK STRUCTURE ALONG SANTO TOMAS RIVER (OMAYA-BALINGCAGUING-PAITE SECTION), SAN NARCISO, ZAMBALES (PHASE 2)On-Going₱48.8M
25CL0135Jun 6, 2025CONSTRUCTION OF ROAD, PUROK 1, BARANGAY DALLIPAWEN, SAN NARCISO, ZAMBALESOn-Going₱19.4M
25CL0188May 23, 2025REHABILITATION OF MULTI-PURPOSE BUILDING, SAN JOSE PATROCINIO ELEMENTARY SCHOOL, SAN NARCISO, ZAMBALESOn-Going₱14.7M
25CL0192May 23, 2025CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG STO. TOMAS RIVER (MACULCOL DIKE) SOUTH APPROACH, PHASE 1, SAN NARCISO, ZAMBALESOn-Going₱96.4M
25CL0193May 23, 2025CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG STO. TOMAS RIVER (MACULCOL DIKE) SOUTH APPROACH, PHASE 2, SAN NARCISO, ZAMBALESOn-Going₱96.5M
25CL0194May 23, 2025CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG STO. TOMAS RIVER (MACULCOL DIKE) SOUTH APPROACH, PHASE 3, SAN NARCISO, ZAMBALESOn-Going₱96.4M
25CL0195May 23, 2025CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG STO. TOMAS RIVER (MACULCOL DIKE) SOUTH APPROACH, PHASE 4, SAN NARCISO, ZAMBALESOn-Going₱96.4M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.