Project 18CL0083
DPWH infrastructure contract
Contract ID:
18CL0083
Fingerprint:
95d0394e3be635…1790784a66 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jul 17, 2018 (8 yrs 4 mo ago) · Target/actual end Sep 14, 2018
Description:
CONSTRUCTION OF RAIN WATER COLLECTOR SYSTEM
Category:
Water Provision and Storage
Implementing office:
DPWH Zambales 1st DEO · Region III
Contractor:
NEW MASINLOC HENRY'S CONSTRUCTION & SUPPLY · DPWH contractor code 33744
Contract amount:
₱3,265,127.24 (₱3.3M)
Funding source:
Regular Infra - GAA 2018 Other Infrastructure (CSSP)
Budget year:
2018
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 2d0e9c55f126… | Jun 28, 2018 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - ZAMBALES 1ST DEO | ₱3,265,127.24 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25CL0256 | Jul 18, 2025 | CONSTRUCTION OF FLOOD CONTROL RIVERBANK STRUCTURE ALONG SANTO TOMAS RIVER (OMAYA-BALINGCAGUING-PAITE SECTION), SAN NARCISO, ZAMBALES (PHASE 1) | On-Going | ₱48.8M |
| 25CL0257 | Jul 18, 2025 | CONSTRUCTION OF FLOOD CONTROL RIVERBANK STRUCTURE ALONG SANTO TOMAS RIVER (OMAYA-BALINGCAGUING-PAITE SECTION), SAN NARCISO, ZAMBALES (PHASE 2) | On-Going | ₱48.8M |
| 25CL0135 | Jun 6, 2025 | CONSTRUCTION OF ROAD, PUROK 1, BARANGAY DALLIPAWEN, SAN NARCISO, ZAMBALES | On-Going | ₱19.4M |
| 25CL0188 | May 23, 2025 | REHABILITATION OF MULTI-PURPOSE BUILDING, SAN JOSE PATROCINIO ELEMENTARY SCHOOL, SAN NARCISO, ZAMBALES | On-Going | ₱14.7M |
| 25CL0192 | May 23, 2025 | CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG STO. TOMAS RIVER (MACULCOL DIKE) SOUTH APPROACH, PHASE 1, SAN NARCISO, ZAMBALES | On-Going | ₱96.4M |
| 25CL0193 | May 23, 2025 | CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG STO. TOMAS RIVER (MACULCOL DIKE) SOUTH APPROACH, PHASE 2, SAN NARCISO, ZAMBALES | On-Going | ₱96.5M |
| 25CL0194 | May 23, 2025 | CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG STO. TOMAS RIVER (MACULCOL DIKE) SOUTH APPROACH, PHASE 3, SAN NARCISO, ZAMBALES | On-Going | ₱96.4M |
| 25CL0195 | May 23, 2025 | CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG STO. TOMAS RIVER (MACULCOL DIKE) SOUTH APPROACH, PHASE 4, SAN NARCISO, ZAMBALES | On-Going | ₱96.4M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.