Project 18CN0007
DPWH infrastructure contract
Contract ID:
18CN0007
Fingerprint:
e574caaec86950…7502dcce40 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 12, 2018 (8 yrs 8 mo ago) · Target/actual end Apr 27, 2018
Description:
CONSTRUCTION OF MULTI-PURPOSE BUILDING (DAY CARE CENTER), PUROK 7, BRGY. KADAYACAN, MARIA AURORA, AURORA PROVINCE
Category:
Buildings and Facilities
Implementing office:
DPWH Aurora DEO · Region III
Contractor:
RADD CONSTRUCTION · DPWH contractor code 9649
Contract amount:
₱1,944,564.79 (₱1.9M)
Funding source:
Regular Infra - GAA 2018 LP
Budget year:
2018
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 774e8d8abb86… | Jan 30, 2018 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - AURORA DEO | ₱1,944,564.79 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25CN0153 | Aug 27, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, MARIA AURORA, AURORA | On-Going | ₱49.0M |
| 25C00484 | Aug 14, 2025 | ASSET PRESERVATION PROGRAM-REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE-SECONDARY ROADS, NUEVA ECIJA-AURORA ROAD, PROVINCE OF AURORA | On-Going | ₱141.9M |
| 25CN0100 | Jul 4, 2025 | CONSTRUCTION OF DRAINAGE CANAL, BARANGAY CADAYACAN, MARIA AURORA, AURORA | Completed | ₱15.4M |
| 25CN0160 | Jul 4, 2025 | CONTRUCTION OF BAYANIHAN - QUIRINO ROAD, MARIA AURORA, AURORA | On-Going | ₱48.0M |
| 25CN0066 | Jun 9, 2025 | CONSTRUCTION OF WATER SYSTEM, BARANGAY PUNGLO, MARIA AURORA, AURORA | On-Going | ₱4.8M |
| 25CN0069 | Jun 9, 2025 | CONSTRUCTION OF ROAD, BARANGAY 2, MARIA AURORA, AURORA | On-Going | ₱9.8M |
| 25CN0027 | May 28, 2025 | REHABILITATION/MAJOR REPAIR OF PERMANENT BRIDGES, DIMANI BR. (B02824LZ) ALONG NUEVA ECIJA - AURORA RD | Completed | ₱7.3M |
| 25CN0015 | May 27, 2025 | REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS, A. CASTAÑEDA - MA AURORA - SN LUIS RD, K0193 + (-040) - K0193 + (-010), K0205 + 250 - K0205 + 275 | Completed | ₱2.3M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.