Project 18CN0024
DPWH infrastructure contract
Contract ID:
18CN0024
Fingerprint:
ab29507ee55910…a4b5d2503f Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Apr 23, 2018 (8 yrs 6 mo ago) · Target/actual end Apr 8, 2019
Description:
NETWORK DEVELOPMENT PROGRAM, OFF-CARRIAGEWAY IMPROVEMENT, BALER-CASIGURAN ROAD (BALER-DINADIAWAN) K0251+000 TO K0252+213, K0252+309 TO K0253+945, K0253+959 TO K0254+160, K0254+173.55 TO K0256+693, K0257+414 TO K0262+970, K0262+995 TO K0264+508, K0264+669
Category:
Roads
Implementing office:
DPWH Aurora DEO · Region III
Contractor:
R.A. PAHATI CONST. & SUPPLY, INC · DPWH contractor code 35843
As listed: R.A. PAHATI CONST. & SUPPLY, INC.
Contract amount:
₱96,500,000.00 (₱96.5M)
Funding source:
Regular Infra - GAA 2018 OO-1
Budget year:
2018
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 5834bed0dca1… | Apr 10, 2018 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - AURORA DEO | ₱93,798.91 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25CN0202 | Nov 4, 2025 | REPAIR/REHABILITATION OF 18 CLASSROOMS, DINADIAWAN ES, DIPACULAO, AURORA | On-Going | ₱14.4M |
| 25CN0010 | Jul 14, 2025 | ASSET PRESERVATION PROGRAM - REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - SECONDARY ROADS, MADELLA - DINADIAWAN RD, K0409 + 303 - K0409 + 309, K0409 + 352 - K0409 + 358, K0411 + 076 - K0411 + 094, K0413 + 060 - K0413 + 114, ........... | Completed | ₱4.0M |
| 25CN0012 | Jul 14, 2025 | REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS, BALER - CASIGURAN RD (BALER - DINADIAWAN), K0249 + 590 - K0249 + 690, K0249 + 830 - K0249 + 860 | On-Going | ₱11.3M |
| 25CN0076 | Jul 4, 2025 | CONSTRUCTION OF ROAD, BARANGAY DIANED, DIPACULAO, AURORA | Completed | ₱9.7M |
| 25C00005 | Jun 23, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES-CONST. OF FLOOD CONTROL STRUCTURE, BRGY. MIJARES, DIPACULAO, AURORA | On-Going | ₱144.7M |
| 25CN0002 | Jun 16, 2025 | ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS BALER-CASIGURAN RD (BALER-DINADIAWAN) - K0248+105 - K0248+689, K0273+450 - K0274+450 | Completed | ₱55.8M |
| 25CN0003 | Jun 9, 2025 | ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS, BALER - CASIGURAN RD (BALER - DINADIAWAN), K0251 + 282 - K0252 + 207, K0269 + 440 - K0269 + 817 | Completed | ₱43.0M |
| 25CN0009 | May 28, 2025 | ASSET PRESERVATION PROGRAM - REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - SECONDARY ROADS, MADELLA-DINADIAWAN RD - K0409+290 - K0409+303, K0409+320 - K0409+352, K0411+043 - K0411+049, K0413+000 - K0413+054, K0418+650 - K0418+750... | Completed | ₱5.2M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.