Project 18CN0050
DPWH infrastructure contract
This contract as an OC4IDS project record, the infrastructure standard used by OpenGovChain. Download: JSON
{
"id": "oc4ids-pisoscan-dpwh-18CN0050",
"title": "CONSTRUCTION OF COVERED COURT OF AURORA DISTRICT ENGINEERING OFFICE INCLUDING SITE DEVELOPMENT AT BARANGAY RESERVA, BALER, AURORA",
"sector": [
"Buildings and Facilities"
],
"status": "completed",
"publicAuthority": {
"name": "DPWH Aurora DEO"
},
"period": {
"startDate": "2018-04-11",
"endDate": "2018-10-28"
},
"budget": {
"amount": {
"amount": 9973353.56,
"currency": "PHP"
}
},
"locations": [
{
"geometry": {
"type": "Point",
"coordinates": [
121.54243,
15.80833
]
}
}
],
"parties": [
{
"name": "TRANS-AURORA CONSTRUCTION",
"roles": [
"supplier"
]
}
],
"contractingProcesses": [
{
"id": "18CN0050",
"summary": {
"title": "CONSTRUCTION OF COVERED COURT OF AURORA DISTRICT ENGINEERING OFFICE INCLUDING SITE DEVELOPMENT AT BARANGAY RESERVA, BALER, AURORA",
"status": "closed",
"contractValue": {
"amount": 9973353.56,
"currency": "PHP"
}
}
}
],
"pisoscan": {
"dpwhStatus": "Completed",
"physicalProgressPercent": 100,
"fundingSource": "Regular Infra - GAA 2018 LP",
"sourceDataset": "DPWH contract list via BetterGov.ph",
"sha256": "bed4f71049145e295f92ff6cb2ba1932f4ca39b1783403d6ddd2450be4883dad"
}
}