Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 18CN0081

DPWH infrastructure contract
Contract ID:
18CN0081
Fingerprint:
0f65f4d7b2b63f…3d78099ca4 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jun 5, 2018 (8 yrs 5 mo ago) · Target/actual end May 2, 2019
Description:
CONSTRUCTION OF DITEKI RIVER CONTROL, BRGY. DIKILDIT, MA. AURORA, AURORA
Category:
Flood Control and Drainage
Implementing office:
DPWH Aurora DEO · Region III
Contract amount:
₱57,900,000.00 (₱57.9M)
Funding source:
Regular Infra - GAA 2018 LP
Budget year:
2018

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25CN0153Aug 27, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, MARIA AURORA, AURORAOn-Going₱49.0M
25C00484Aug 14, 2025ASSET PRESERVATION PROGRAM-REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE-SECONDARY ROADS, NUEVA ECIJA-AURORA ROAD, PROVINCE OF AURORAOn-Going₱141.9M
25CN0100Jul 4, 2025CONSTRUCTION OF DRAINAGE CANAL, BARANGAY CADAYACAN, MARIA AURORA, AURORACompleted₱15.4M
25CN0160Jul 4, 2025CONTRUCTION OF BAYANIHAN - QUIRINO ROAD, MARIA AURORA, AURORAOn-Going₱48.0M
25CN0066Jun 9, 2025CONSTRUCTION OF WATER SYSTEM, BARANGAY PUNGLO, MARIA AURORA, AURORAOn-Going₱4.8M
25CN0069Jun 9, 2025CONSTRUCTION OF ROAD, BARANGAY 2, MARIA AURORA, AURORAOn-Going₱9.8M
25CN0027May 28, 2025REHABILITATION/MAJOR REPAIR OF PERMANENT BRIDGES, DIMANI BR. (B02824LZ) ALONG NUEVA ECIJA - AURORA RDCompleted₱7.3M
25CN0015May 27, 2025REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS, A. CASTAÑEDA - MA AURORA - SN LUIS RD, K0193 + (-040) - K0193 + (-010), K0205 + 250 - K0205 + 275Completed₱2.3M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.