DPWH infrastructure contract
Contract ID:
18DB0219
Fingerprint:
9b6abca73bbb50…a92b185917 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Aug 1, 2018 (8 yrs 3 mo ago) · Target/actual end Oct 5, 2019
Description:
CONSTRUCTION AND COMPLETION OF SCHOOL BUILDING TWO (2) STOREY SIX (6) CLASSROOM AT TULO ES, TAAL, BATANGAS
Category:
Buildings and Facilities
Implementing office:
DPWH Batangas 1st DEO · Region IV-A
Contractor:
FILCAN UNITED CONSTRUCTION & GENERAL MERCHANDISE CORP. · DPWH contractor code 40838
Contract amount:
₱11,759,077.17 (₱11.8M)
Funding source:
Outside Infra - GAA 2018 DepEd BEFF
Budget year:
2018
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 74962e7c75b6… | Jul 16, 2018 | DPWH BATANGAS I DISTRICT ENGINEERING OFFICE | ₱11,641,486.41 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25DB0177 | Aug 27, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - COMPLETION OF MULTI-PURPOSE BUILDING (COVERED COURT) AT BARANGAY CAWIT, TAAL, BATANGAS | Completed | ₱1.9M |
| 25DB0165 | Jul 25, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - COMPLETION OF MULTI-PURPOSE BUILDING IN CUBAMBA-GAHOL INTEGRATED SCHOOL, TAAL, BATANGAS | Completed | ₱2.9M |
| 25DB0195 | Jul 21, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING (YOUTH CENTER) AT CARASUCHE, TAAL, BATANGAS | On-Going | ₱19.2M |
| 25DB0179 | Jul 9, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - COMPLETION OF MULTI-PURPOSE BUILDING AT BARANGAY ZONE 2, TAAL, BATANGAS | Completed | ₱2.0M |
| 25DB0127 | Jul 7, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF ROAD, BRGY. ILOG, TAAL, BATANGAS | Completed | ₱4.8M |
| 25DB0128 | Jul 7, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF ROAD, BRGY. MAHABANG LUDLOD, TAAL, BATANGAS | Completed | ₱4.8M |
| 25DB0176 | Jul 7, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - COMPLETION OF MULTI-PURPOSE BUILDING (COVERED COURT) AT BARANGAY APACAY, TAAL, BATANGAS | Completed | ₱1.9M |
| 25DB0178 | Jul 7, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - COMPLETION OF MULTI-PURPOSE BUILDING (COVERED COURT) AT BARANGAY PANSOL, TAAL, BATANGAS | Completed | ₱1.9M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.