Project 18DE0134
DPWH infrastructure contract
Contract ID:
18DE0134
Fingerprint:
8ca5b067ae2b0f…ee25b3d7e0 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Apr 23, 2018 (8 yrs 6 mo ago) · Target/actual end Aug 31, 2019
Description:
CONSTRUCTION OF LUYA BRIDGE, BARANGAY LUYA, SAN LUIS, BATANGAS
Category:
Bridges
Implementing office:
DPWH Batangas 2nd DEO · Region IV-A
Contractor:
C.S. RAYOS CONSTRUCTION & GENERAL SERVICES, INC. (9790) / HEREFOLD BUILDERS & CONSTRUCTION SUPPLY · DPWH contractor code 20789
Contract amount:
₱17,820,000.00 (₱17.8M)
Funding source:
Regular Infra - GAA 2018 LP
Budget year:
2018
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25DE0182 | Jun 9, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), PUBLIC WATER SUPPLY SYSTEM, CONSTRUCTION (COMPLETION) OF WATER SYSTEM INCLUDING GENERATOR SET AT BARANGAY LOCLOC, SAN LUIS, BATANGAS | Completed | ₱4.8M |
| 25DE0079 | May 26, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), PUBLIC WATER SUPPLY SYSTEM, CONSTRUCTION OF WATER SUPPLY SYSTEM (WATER WORKS), BARANGAY ABIACAO, SAN LUIS, BATANGAS | On-Going | ₱4.8M |
| 25DE0089 | May 26, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION/REHABILITATION OF MULTI-PURPOSE BUILDING (COVERED COURT) SAN MARTIN, SAN LUIS BATANGAS | Completed | ₱4.8M |
| 25DE0125 | May 26, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (COVERED COURT) AT BRGY. TUNGAL, SAN LUIS, BATANGAS | Completed | ₱9.6M |
| 25DE0128 | May 26, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (COVERED COURT) AT BARANGAY CALUMPANG WEST, SAN LUIS, BATANGAS | Completed | ₱14.8M |
| 25DE0095 | May 20, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, IMPROVEMENT OF ROAD, DULANGAN-TALON-ABIACAO | Completed | ₱144.8M |
| 25DE0096 | May 20, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, IMPROVEMENT OF ROAD, MANGGAHAN-SAN MARTIN-S | Completed | ₱144.8M |
| 25DE0097 | May 20, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, IMPROVEMENT OF ROAD, BAGONG TUBIG-SAN ISIDR | Completed | ₱144.8M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.