Project 18DJ0082
DPWH infrastructure contract
Contract ID:
18DJ0082
Fingerprint:
81df96b7823968…92c89b9775 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jun 4, 2018 (8 yrs 5 mo ago) · Target/actual end Oct 1, 2018
Description:
CONCRETING OF BRGY. BUKAL NORTE FMR, BRGY. BUKAL NORTE, CANDELARIA, QUEZON
Category:
Roads
Implementing office:
DPWH Quezon 2nd DEO · Region IV-A
Contractor:
G.T.J. CONSTRUCTION · DPWH contractor code 42452
Contract amount:
₱9,949,999.72 (₱9.9M)
Funding source:
Outside Infra - GAA 2018 DA FMR
Budget year:
2018
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| a57c0d1ba9e9… | May 25, 2018 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - QUEZON 2ND ED | ₱9,600,559.60 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25DJ0146 | Aug 29, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING PHASE 3, BARANGAY PAHINGA NORTE, CANDELARIA, QUEZON | On-Going | ₱48.0M |
| 25DJ0024 | Jun 5, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF ROAD, BARANGAY BUKAL NORTE, CANDELARIA, QUEZON | Completed | ₱4.8M |
| 25DJ0025 | Jun 5, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF ROAD, BARANGAY MANGILAG SUR, CANDELARIA, QUEZON | On-Going | ₱4.9M |
| 25DJ0026 | Jun 5, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF ROAD, BARANGAY MASALUKOT 2, CANDELARIA, QUEZON | Completed | ₱5.8M |
| 25DJ0054 | Jun 5, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDING/FACILITIES, CONSTRUCTION OF ROAD, BARANGAY MAYABOBO, CANDELARIA, QUEZON | Completed | ₱4.8M |
| 25DJ0074 | Jun 5, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF ROAD, BARANGAY PAHINGA NORTE, CANDELARIA, QUEZON | On-Going | ₱4.8M |
| 25DJ0109 | Jun 5, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP) - PUBLIC WATER SUPPLY SYSTEM, CONSTRUCTION OF WATER SUPPLY SYSTEM, BARANGAY POBLACION, CANDELARIA, QUEZON | On-Going | ₱9.6M |
| 25DJ0113 | Jun 5, 2025 | OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - SECONDARY ROADS, CANDELARIA BYPASS RD - K0106+935 - K0107+124.5 | On-Going | ₱18.1M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.