Project 18DL0012
DPWH infrastructure contract
Contract ID:
18DL0012
Fingerprint:
c200f4aeb81168…a55db49823 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 15, 2018 (8 yrs 9 mo ago) · Target/actual end May 15, 2018
Description:
I. OPERATIONS A. ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM 3. BRIDGE PROGRAM A. RETROFITTING / STRENGTHENING OF PERMANENT BRIDGES 2. BOONG SUR BR. (B00031AB) ALONG QUEZON-ALABAT-PEREZ RD
Category:
Bridges
Implementing office:
DPWH Quezon 4th DEO · Region IV-A
Contractor:
JEMAK CONSTRUCTION & SUPPLY · DPWH contractor code 32056
Contract amount:
₱3,813,738.91 (₱3.8M)
Funding source:
Regular Infra - GAA 2018 OO-1
Budget year:
2018
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 4215ef707d33… | Jan 29, 2018 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - QUEZON 4TH ED | ₱3,813,738.91 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25DL0190 | Jul 4, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), BIP - EVACUATION CENTERS/ QUARANTINE FACILITIES/ PUBLIC HEALTH FACILITIES, CONSTRUCTION OF ALABAT DISTRICT HOSPITAL, ALABAT, QUEZON | Completed | ₱96.0M |
| 25DL0152 | May 26, 2025 | ORGANIZATIONAL OUTCOME 2 : PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF BREAKWATER, ALABAT, QUEZON | Completed | ₱9.5M |
| 25DL0154 | May 26, 2025 | ORGANIZATIONAL OUTCOME 2 : PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF FLOOD CONTROL ALONG CAGLATE RIVER, ALABAT, QUEZON | Completed | ₱4.8M |
| 25DL0155 | May 26, 2025 | FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BOONG RIVER, BARANGAYS VILLA VICTORIA AND BACONG, ALABAT, QUEZON | Completed | ₱4.8M |
| 25DL0046 | Apr 8, 2025 | ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM, CONSTRUCTION OF MISSING LINKS/ NEW ROADS, QUEZON - ALABAT - PEREZ CIRCUMFERENTIAL ROAD, PACKAGE A, QUEZON | Completed | ₱28.8M |
| 25DL0066 | Apr 8, 2025 | CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM - TRIP), SITIO CANUMAY-TUMIIS ECOTOURISM ROAD LEADING TO ALABAT ISLAND, BRGY. VILLA NORTE, ALABAT, QUEZON | Completed | ₱4.8M |
| 25DL0026 | Apr 7, 2025 | CONSTRUCTION OF BRIDGE, BARANGAY POBLACION 2 - BARANGAY POBLACION 3, ALABAT, QUEZON | On-Going | ₱24.0M |
| 25DL0030 | Apr 7, 2025 | CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES (ROADS LEVERAGING LINKAGES FOR INDUSTRY AND TRADE INFRASTRUCTURE PROGRAM - ROLL-IT), ACCESS ROADS IN SUPPORT OF COCO SUGAR PROCESSING CENTER, ALABAT, QUEZON | Completed | ₱9.6M |