Project 18DM0047
DPWH infrastructure contract
Contract ID:
18DM0047
Fingerprint:
f6bef9da07bfa8…e3afd10ce2 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 20, 2018 (8 yrs 8 mo ago) · Target/actual end Dec 6, 2018
Description:
CONSTRUCTION OF ROAD SLOPE PROTECTION STRUCTURE - SN FRANCISCO - SN ANDRES - SN NARCISO RD - K0365+603 - K0365+623, K0372+327 - K0372+360, K0375+620 - K0375+656, K0376+039 - K0376+184, K0379+080 - K0379+150, K0379+920 - K0379+945, K0382+577 - K0382+622
Category:
Roads
Implementing office:
DPWH Quezon 3rd DEO · Region IV-A
Contractor:
RAPID FOREMOST CONST. CO. · DPWH contractor code 32618
Contract amount:
₱31,360,000.00 (₱31.4M)
Funding source:
Regular Infra - GAA 2018 OO-1
Budget year:
2018
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 4690a42242d3… | Jan 19, 2018 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - QUEZON 3RD ED | ₱30,733,597.81 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25DM0167 | Sep 5, 2025 | CONCRETING OF POBLACION TO SITIO BANABA, BRGY. PANSOY FMR, BRGY. PANSOY, SAN ANDRES, QUEZON | Completed | ₱14.9M |
| 25DM0140 | Aug 13, 2025 | CONSTRUCTION OF ROAD, MABATO - PANSOY, PACKAGE D, SAN ANDRES, QUEZON | On-Going | ₱77.2M |
| 25DM0136 | Jun 5, 2025 | CONSTRUCTION OF ROAD AT SITIO NABAROTO, BRGY. CAMFLORA, SAN ANDRES, QUEZON | Completed | ₱34.6M |
| 25DM0142 | Jun 5, 2025 | CONSTRUCTION OF ROAD AT SITIO KABASYARAN- SITIO BAG-AS, BARANGAY MANGERO AND BARANGAY TALISAY, SAN ANDRES, QUEZON | Completed | ₱29.7M |
| 25DM0093 | Jun 3, 2025 | CONSTRUCTION/REHABILITATION OF WATER SUPPLY/SEPTAGE AND SEWERAGE/RAINWATER COLLECTOR SYSTEM | Completed | ₱2.5M |
| 25DM0109 | May 21, 2025 | ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS - SN FRANCISCO- SN ANDRES-SN NARCISO RD - K0366+125 - K0366+825, K0368+264 - K0369+000, K0372+581 - K0373+955, K0374+289 - K0375+000 | Completed | ₱93.6M |
| 25DM0127 | May 21, 2025 | ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS - SN FRANCISCO-SN ANDRES-SN NARCISO RD - K0353 + 000 - K0355 + 000 | On-Going | ₱93.8M |
| 25DM0133 | May 21, 2025 | ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS - SN FRANCISCO-SN ANDRES-SN NARCISO RD - K0355 + 000 - K0357 + 000 | On-Going | ₱93.9M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.