Project 18DN0003
DPWH infrastructure contract
Contract ID:
18DN0003
Fingerprint:
997ad2cc093d3d…b33bd9852f Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 21, 2018 (8 yrs 8 mo ago) · Target/actual end Mar 12, 2018
Description:
001- ASSET PRESERVATION-PREVENTIVE MAINTENANCE-TERTIARY ROADS MANILA EAST ROAD (S01744LZ) K0023+704-K0024+300, TAYTAY, RIZAL
Category:
Roads
Implementing office:
DPWH Rizal 1st DEO · Region IV-A
Contractor:
A.J. LAVA BUILDERS CORP. (FORMERLY: A.J. LAVA BUIL · DPWH contractor code 22265
Contract amount:
₱6,740,680.38 (₱6.7M)
Funding source:
Regular Infra - GAA 2018 OO-1
Budget year:
2018
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25O00107 | Jun 5, 2025 | REHABILITATION AND IMPROVEMENT OF RETARDING POND AT TAPAYAN PUMPING STATION AND TRIBUTARIES, PASIG CITY | On-Going | ₱189.1M |
| 25OB0268 | May 20, 2025 | REHABILITATION OF DRAINAGE SYSTEM AT BARANGAY PINAGBUHATAN, PASIG CITY (PHASE 5) | On-Going | ₱14.0M |
| 25OB0269 | May 20, 2025 | REHABILITATION OF DRAINAGE SYSTEM AT BARANGAY PINAGBUHATAN, PASIG CITY (PHASE 6) | On-Going | ₱14.0M |
| 25OB0270 | May 20, 2025 | REHABILITATION OF DRAINAGE SYSTEM AT BARANGAY PINAGBUHATAN, PASIG CITY (PHASE 7) | On-Going | ₱14.0M |
| 25DN0069 | Apr 8, 2025 | CONSTRUCTION OF ROAD AT ROAD 11, 12, 13, 14, 15, 16 AND 17, PUROK 3, LUPANG ARENDA, BARANGAY STA. ANA, TAYTAY, RIZAL (FIRST DISTRICT) | On-Going | ₱19.6M |
| 25DN0063 | Mar 27, 2025 | CONSTRUCTION OF MULTI-PURPOSE FACILITY, RIZAL POLICE PROVINCIAL OFFICE, BARANGAY DOLORES, TAYTAY, RIZAL (FIRST DISTRICT) | On-Going | ₱9.7M |
| 25DN0080 | Mar 27, 2025 | CONSTRUCTION OF ROAD AT BLK. 16 AND 17, PUROK 2 LUPANG ARENDA, BARANGAY STA. ANA, TAYTAY, RIZAL (FIRST DISTRICT) | On-Going | ₱15.2M |
| 25DN0048 | Mar 26, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT TAYTAY RIVER, BARANGAY STA. ANA, TAYTAY, RIZAL (FIRST DISTRICT) | On-Going | ₱49.0M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.