FY2026 GAA: ₱6.79T
PisoScan

Project 18DQ0039

DPWH infrastructure contract
Hashed input (canonical JSON of the source row)
["dpwh","18DQ0039","ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINSTMAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS:CONSTRUCTION OF REVETMENT ALONG BALUCTOT RIVER, PHASE LLL, WEST SIDE","GAA 2018 OO-2","Completed",46312278.2,0,100,"Region IV-A","Region IV-A","CBS CONSTRUCTION AND CONSTRUCTION SUPPLY (30244) / HAUSLAND CONSTRUCTION (32378)","2018-03-15","2019-01-08",2018,"Regular Infra - GAA 2018 OO-2",14.31979,120.9784,"402106000","402100000"]
SHA-256
c7050ff1ecb62ecb60ae475fb46100f18b64dd6497da016b0141df734ac55f73