Project 18DQ0130
DPWH infrastructure contract
Contract ID:
18DQ0130
Fingerprint:
4f9b62bee18569…7345a22565 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jan 14, 2019 (7 yrs 10 mo ago) · Target/actual end Sep 10, 2019
Description:
CONSTRUCTION OF RAIN WATER COLLECTION SYSTEM (RWCS) KAONG NATIONAL HIGH SCHOOL, BRGY. KAONG, SILANG, CAVITE, BULIHAN SITES AND SERVICES PROJECT ELEMENTARY SCHOOL, BRGY. BULIHAN, SILANG, CAVITE, BULIHAN NATIONAL HIGH SCHOOL, BRGY. BULIHAN, SILANG, CAVITE,
Category:
Water Provision and Storage
Implementing office:
DPWH Region IV-A · Region IV-A
Contractor:
OMNICON BUILDERS · DPWH contractor code 22816
Contract amount:
₱3,231,359.17 (₱3.2M)
Funding source:
Regular Infra - GAA 2018 Other Infrastructure (CSSP)
Budget year:
2018
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25DQ0110 | Jul 3, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY MALIKSI 2, BACOOR CITY, CAVITE | On-Going | ₱9.8M |
| 25DQ0111 | Jul 3, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY BAYANAN, BACOOR CITY, CAVITE | On-Going | ₱9.8M |
| 25DF0158 | Jul 1, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAMBASIC INFRASTRUCTURE PROGRAM (BIP)ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITESCONSTRUCTION OF ROAD WITH DRAINAGE AT BRGY. PALICO IV, CITY OF IMUS, | On-Going | ₱4.8M |
| 25DQ0084 | Jun 17, 2025 | CONSTRUCTION OF RIVERWALL AND OTHER IMPROVEMENT WORKS ALONG BACOOR RIVER, PHASE 1, CITY OF BACOOR, CAVITE | On-Going | ₱96.0M |
| 25DQ0085 | Jun 17, 2025 | CONSTRUCTION OF RIVERWALL AND OTHER IMPROVEMENT WORKS ALONG BACOOR RIVER, PHASE 2, CITY OF BACOOR, CAVITE | On-Going | ₱98.0M |
| 25DQ0090 | Jun 17, 2025 | CONSTRUCTION OF SLOPE AND BANKS PROTECTION WORKS ALONG BACOOR RIVER, CITY OF BACOOR, CAVITE (PHASE 1) | On-Going | ₱98.0M |
| 25DQ0099 | Jun 17, 2025 | CONSTRUCTION OF SLOPE AND BANKS PROTECTION WORKS ALONG BACOOR RIVER, CITY OF BACOOR, CAVITE (PHASE 3) | On-Going | ₱98.0M |
| 25DQ0101 | Jun 17, 2025 | CONSTRUCTION OF SLOPE AND BANKS PROTECTION WORKS ALONG BACOOR RIVER, CITY OF BACOOR, CAVITE (PHASE 2) | On-Going | ₱98.0M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.