Project 18EA0098
DPWH infrastructure contract
Contract ID:
18EA0098
Fingerprint:
abb3a90515e33b…8d623ba8cc Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start May 31, 2018 (8 yrs 5 mo ago) · Target/actual end Dec 28, 2018
Description:
PACKAGE 22-A)CONCRETING OF BRGY. ANTIPOLO-CALONG ROAD,GASAN, MARINDUQUE,B)CONCRETING OF BRGY. MATAND
Category:
GAA 2018 LP
Implementing office:
DPWH Marinduque DEO · MIMAROPA Region
Contractor:
KENNETH CONSTRUCTION AND GENERAL MERCHANDISE · DPWH contractor code 33441
Contract amount:
₱8,732,797.17 (₱8.7M)
Funding source:
Regular Infra - GAA 2018 LP
Budget year:
2018
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 9ad31bc339f2… | May 22, 2018 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - MARINDUQUE DEO | ₱8,555,362.61 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25EA0046 | Jun 23, 2025 | BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BRGY. CAIGANGAN, BUENAVISTA, MARINDUQUE | Completed | ₱6.8M |
| 25EA0025 | May 23, 2025 | BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING (PHASE 2), BARANGAY YOOK, BUENAVISTA, MARINDUQUE | Completed | ₱2.9M |
| 25EA0017 | Mar 21, 2025 | NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING-SECONDARY ROADS, MARINDUQUE CIRCUMFERENTIAL RD - K0081+598-K0082+000, K0082+761 - K0083+000, K0086+000-K0087+398 | On-Going | ₱108.0M |
| 25EA0024 | Mar 21, 2025 | BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (PHASE 2), BARANGAY DAYKITIN, BUENAVISTA, MARINDUQUE | Completed | ₱3.7M |
| 25EA0034 | Mar 21, 2025 | BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING, BUENAVISTA CENTRAL SCHOOL, BUENAVISTA, MARINDUQUE | Completed | ₱13.4M |
| 25EA0047 | Feb 21, 2025 | FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF PROTECTION WORKS, BAGTINGON SRIP, BUENAVISTA, MARINDUQUE | Completed | ₱14.4M |
| 25EA0048 | Feb 21, 2025 | FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEM, CONSTRUCTION OF BAGTINGON FLOOD CONTROL STRUCTURE, BARANGAY BAGTINGON, BUENAVISTA, MARINDUQUE | Completed | ₱43.2M |
| 24E00005 | Mar 2, 2024 | BASIC INFRASTRUCTURE PROGRAM (BIP)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF BUENAVISTA SHORE PROTECTION, BUENAVISTA, MARINDUQUE | On-Going | ₱238.9M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.