Project 18ED0081
DPWH infrastructure contract
Contract ID:
18ED0081
Fingerprint:
44b4bc6625b1a1…cf6579c7a4 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Apr 22, 2018 (8 yrs 6 mo ago) · Target/actual end Oct 26, 2018
Description:
CONSTRUCTION OF POLA - NAUJAN BYPASS ROAD, POLA, ORIENTAL MINDORO
Category:
GAA 2018 OO-1
Implementing office:
DPWH Mindoro Oriental DEO · MIMAROPA Region
Contractor:
RICH ADS CONSTRUCTION CORP. (FORMERLY RICH ADS CON · DPWH contractor code 31157
Contract amount:
₱46,891,986.42 (₱46.9M)
Funding source:
Regular Infra - GAA 2018 OO-1
Budget year:
2018
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25ED0135 | May 26, 2025 | REHABILITATION OF BRGY. MALUANLUAN - BRGY. MALIBAGO ROAD, POLA, ORIENTAL MINDORO | Completed | ₱144.1M |
| 25ED0112 | May 21, 2025 | CONSTRUCTION OF KABILANG IBAYO BRIDGE, BRGY. BATUHAN, POLA, ORIENTAL MINDORO | On-Going | ₱34.6M |
| 25ED0162 | May 21, 2025 | REHABILITATION OF MULTI - PURPOSE BUILDING (MUNICIPAL GYMNASIUM) IN POLA, ORIENTAL MINDORO | Completed | ₱14.4M |
| 25ED0178 | May 21, 2025 | REHABILITATION OF DRAINAGE CANAL AT SITIO SAMPALOCAN CAMPAMENTO, POLA, ORIENTAL MINDORO | Completed | ₱4.9M |
| 25E00224 | Apr 6, 2025 | BRIDGE PROGRAM- CASILIGAN BRIDGE (B00028MR) ALONG CSR JCT. - POLA ROAD, POL;A, OR. MINDORO | On-Going | ₱24.6M |
| 25EI0105 | Mar 25, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (EVACUATION CENTER) AT BARANGAY PILI, PINAMALAYAN, ORIENTAL MINDORO | Completed | ₱4.9M |
| 25ED0099 | Mar 18, 2025 | REHABILITATION OF BRIDGE, KABILANG IBAYO, BARANGAY BATUHAN, POLA, ORIENTAL MINDORO | On-Going | ₱14.7M |
| 25ED0054 | Feb 28, 2025 | CONSTRUCTION OF MULTI - PURPOSE BUILDING, BARANGAY BACAWAN, POLA, ORIENTAL MINDORO | Completed | ₱4.9M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.