Project 18EE0267
DPWH infrastructure contract
Contract ID:
18EE0267
Fingerprint:
8cc485f7185b06…d502e567ea Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Oct 23, 2018 (8 yrs ago) · Target/actual end Dec 1, 2020
Description:
CONSTRUCTION OF THREE-STOREY 9 CLASSROOMS (2 REG. WORKSHOP AND 5 REG. CLASSROOMS) CONCEPCION NATIONAL HIGH SCHOOL, AGUTAYA, PALAWAN
Category:
GAA 2018 DepEd BEFF
Implementing office:
DPWH Palawan 1st DEO · MIMAROPA Region
Contractor:
MARYKNOLL BUILDERS AND SUPPLY · DPWH contractor code 40541
Location:
Contract amount:
₱25,258,390.07 (₱25.3M)
Funding source:
Outside Infra - GAA 2018 DepEd BEFF
Budget year:
2018
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 3c9dad5fd13c… | Oct 5, 2018 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - PALAWAN 1ST DEO | ₱25,258,390.07 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 24EE0092 | May 20, 2024 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY MANAMOC,CUYO, PALAWAN | On-Going | ₱9.6M |
| 24EE0095 | Feb 29, 2024 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, PALAWAN STATE UNIVERSITY CUYO CAMPUS, CUYO, PALAWAN | On-Going | ₱11.9M |
| 23EE0098 | May 14, 2023 | CONSTRUCTION OF LEVEL II WATER SUPPLY SYSTEM IN CUYO CUYO, PALAWAN | On-Going | ₱49.0M |
| 23EE0086 | Apr 30, 2023 | INSTALLATION OF SOLAR STREETLIGHTS BRGY. MANAMOC, CUYO, PALAWAN | Completed | ₱9.6M |
| 23EE0025 | Feb 15, 2023 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY LAGAORIAO CUYO, PALAWAN | Completed | ₱9.9M |
| 22EE0060 | Jun 12, 2022 | CONSTRUCTION OF SUBA-PAWA-SAN CARLOS ROAD CUYO, PALAWAN | Completed | ₱11.9M |
| 22EE0076 | Jun 12, 2022 | CONSTRUCTION OF MULTI-PURPOSE BUILDING BARANGAY LUNGSOD, CUYO, PALAWAN | Completed | ₱9.7M |
| 21EE0110 | Feb 28, 2022 | UPGRADING OF LUNGSOD-LAGAORIAO FARM TO MARKET ROAD, CUYO, PALAWAN | Completed | ₱14.8M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.