Project 18EH0009

DPWH infrastructure contract
Hashed input (canonical JSON of the source row)
["dpwh","18EH0009","CONSTRUCTION OF AGUTAY FLOOD CONTROL STRUCTURE, MAGDIWANG, ROMBLON","GAA 2018 OO-2","Completed",45450500.78,0,100,"Romblon DEO","MIMAROPA Region","LEGACY CONSTRUCTION CORPORATION (FORMERLY: LEGACY CONSTRUCTION) (22465)","2018-03-05","2018-12-14",2018,"Regular Infra - GAA 2018 OO-2",12.462,122.44436,"1705908000","1705900000"]
SHA-256
79b6d0b4370280618eb5833ef0988a731e265b1f03c288d03a1e315d6f7c6485