Project 18EH0102
DPWH infrastructure contract
Contract ID:
18EH0102
Fingerprint:
2997e8f666988e…09682aecae Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jul 16, 2018 (8 yrs 4 mo ago) · Target/actual end Aug 29, 2018
Description:
IMPROVEMENT/REHABILITATION OF ROAD, BRGY. MABINI, CORCUERA, ROMBLON
Category:
GAA 2018 LP
Implementing office:
DPWH Romblon DEO · MIMAROPA Region
Contractor:
TWIN DRAGON CONSTRUCTION · DPWH contractor code 11392
Location:
Contract amount:
₱2,407,719.00 (₱2.4M)
Funding source:
Regular Infra - GAA 2018 LP
Budget year:
2018
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| ce99b929b7f4… | Jun 20, 2018 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - ROMBLON DEO | ₱2,407,719.00 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25EH0013 | Mar 27, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY ALEGRIA, CORCUERA, ROMBLON | Completed | ₱4.9M |
| 25EH0002 | Mar 25, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY TACASAN, CORCUERA, ROMBLON | Completed | ₱4.9M |
| 25EH0017 | Mar 24, 2025 | ACCESS ROAD LEADING TO SUBA COVE, BRGY. SAN ROQUE, MANGANSAG AND MABINI COLONG-COLONG BEACH, CORCUERA, ROMBLON | Completed | ₱9.7M |
| 24E00284 | Oct 25, 2024 | LGU HOSPITALS - MALIPAYON DISTRICT HOSPITAL, MALIPAYON, ROMBLON | On-Going | ₱6.8M |
| 24EH0159 | Aug 9, 2024 | ACCESS ROAD LEADING TO SUBA COVE, BRGY. SAN ROQUE, MANGANSAG AND MABINI COLONG-COLONG BEACH, CORCUERA, ROMBLON | Completed | ₱33.8M |
| 24EH0113 | Apr 8, 2024 | REHABILITATION OF ACCESS ROADS, BRGY. GUINTIGIBAN, CORCUERA, ROMBLON | Completed | ₱5.0M |
| 23EH0161 | Aug 18, 2023 | CONSTRUCTION OF 2STY4CL, MAURICIO F. FABITO NATIONAL HIGH SCHOOL, CORCUERA, ROMBLON | Completed | ₱17.5M |
| 23EH0149 | Aug 10, 2023 | CONSTRUCTION OF SOLAR WATER SYSTEM, CORCUERA, ROMBLON | Completed | ₱9.8M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.