Project 18EH0131
DPWH infrastructure contract
Contract ID:
18EH0131
Fingerprint:
5a9cd3630da88f…4acb1223fc Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Nov 15, 2018 (8 yrs ago) · Target/actual end May 3, 2019
Description:
CONCRETING/CONSTRUCTION OF SITIO LANUTON FMR, BRGY. TAN - AGAN, SAN ANDRES, ROMBLON
Category:
GAA 2018 DA FMR
Implementing office:
DPWH Romblon DEO · MIMAROPA Region
Contractor:
TRIPLE PEAK MOUNTAIN CONSTRUCTION AND SUPPLY · DPWH contractor code 43000
As listed: TRIPLE PEAK MOUNTAIN CONSTRUCTION & SUPPLY
Contract amount:
₱6,845,264.45 (₱6.8M)
Funding source:
Outside Infra - GAA 2018 DA FMR
Budget year:
2018
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25EH0167 | Jul 29, 2025 | CONSTRUCTION OF 7 RAINWATER COLLECTION SYSTEM (RWCS), TABLAS ISLAND, ROMBLON | Completed | ₱2.6M |
| 25EH0151 | May 27, 2025 | CONSTRUCTION OF ROAD, AGPUDLOS LEADING TO RSU ROAD (PHASE 3), SAN ANDRES, ROMBLON | On-Going | ₱46.7M |
| 25EH0121 | May 21, 2025 | CONSTRUCTION OF VICTORIA RIVER FLOOD CONTROL STRUCTURE, SAN ANDRES, ROMBLON | On-Going | ₱119.4M |
| 25EH0030 | Apr 11, 2025 | CONSTRUCTION OF MABINI FLOOD CONTROL STRUCTURE, BARANGAY MABINI, SAN ANDRES, ROMBLON | On-Going | ₱48.3M |
| 25EH0090 | Apr 10, 2025 | CONSTRUCTION OF MARI-SUR FLOOD CONTROL STRUCTURE (RIGHT SIDE), SAN ANDRES, ROMBLON | On-Going | ₱48.3M |
| 25EH0012 | Mar 24, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (BARANGAY HALL), BARANGAY VICTORIA, SAN ANDRES, ROMBLON | Completed | ₱4.9M |
| 25EH0062 | Mar 3, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY MABINI, SAN ANDRES, ROMBLON | Completed | ₱2.9M |
| 24EH0131 | Jun 19, 2024 | REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE ALONG PARPAGOHA (MARIGONDON)-BINOOG RD, K0020+900.00 - K0020+985.60, TABLAS ISLAND, ROMBLON | On-Going | ₱82.0M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.