Project 18EI0163
DPWH infrastructure contract
Contract ID:
18EI0163
Fingerprint:
fa680a7016eee8…600d7d32be Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jan 21, 2019 (7 yrs 9 mo ago) · Target/actual end Jun 29, 2019
Description:
CONSTRUCTION OF 1 UNIT 1 STY 2 CL & 1 UNIT 1 STY 3 CL AT MANSALAY CS, MANSALAY, ORIENTAL MINDORO
Category:
GAA 2018 DepEd BEFF
Implementing office:
DPWH Southern Mindoro DEO · MIMAROPA Region
Contractor:
AIDFELART CONST. CORP. · DPWH contractor code 38811
Contract amount:
₱6,875,700.84 (₱6.9M)
Funding source:
Outside Infra - GAA 2018 DepEd BEFF
Budget year:
2018
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 2f00d9d3ab52… | Dec 21, 2018 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - SOUTHERN MINDORO E | ₱3,875,700.84 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 26EI0128 | Jul 7, 2026 | ROAD WIDENING - SECONDARY ROADS CALAPAN SOUTH RD - K0142+ 019 - K0142 + 134, K0142 + 371 - K0142 + 726, K0143 + 577 - K0143 + 714, K0143 + 847 - K0144 + 011, K0146 + 535 - K0146 + 751, K0151 + 104 - K0151 + 167, MANSALAY, ORIENTAL MINDORO | On-Going | ₱43.0M |
| 25EI0065 | Mar 25, 2025 | PREVENTIVE MAINTENANCE - SECONDARY ROADS - ALONG CALAPAN SOUTH RD. K0153+000 - K0153+493, MANSALAY, ORIENTAL MINDORO | Completed | ₱34.2M |
| 25EI0066 | Mar 25, 2025 | CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF WASIG RIVER CONTROL STRUCTURE, BARANGAY WASIG, MANSALAY, ORIENTAL MINDORO | Completed | ₱29.0M |
| 25EI0076 | Mar 25, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (SK BUILDING) AT BARANGAY POBLACION, MANSALAY, ORIENTAL MINDORO | Completed | ₱4.9M |
| 25EI0104 | Mar 25, 2025 | CONSTRUCTION(COMPLETION) OF MULTI-PURPOSE BUILDING AT BARANGAY BONBON, MANSALAY, ORIENTAL MINDORO, PHASE II | Completed | ₱2.9M |
| 25EI0109 | Mar 25, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT) AT BALUGO NATIONAL HIGH SCHOOL, BARANGAY BALUGO, MANSALAY, ORIENTAL MINDORO, PHASE II | Completed | ₱4.9M |
| 25EI0134 | Mar 25, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING AT BARANGAY B. DEL MUNDO, MANSALAY, ORIENTAL MINDORO, PHASE II | Completed | ₱2.9M |
| 25EI0003 | Mar 13, 2025 | CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - SECONDARY ROADS - CALAPAN SOUTH RD - K0153+480 - K0153+861, MANSALAY, ORIENTAL MINDORO | Completed | ₱13.4M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.