Project 18FN0061
DPWH infrastructure contract
Contract ID:
18FN0061
Fingerprint:
9f84895c325d79…cef7cfd25b Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start May 4, 2018 (8 yrs 6 mo ago) · Target/actual end Oct 12, 2018
Description:
CONSTRUCTION OF RAINWATER COLLECTION SYSTEM (RWCS), DEL GALLEGO AND CABUSAO, CAMARINES SUR
Category:
Water Provision and Storage
Implementing office:
DPWH Camarines Sur 1st DEO · Region V
Contractor:
JMLD CONSTRUCTION · DPWH contractor code 22679
Contract amount:
₱3,156,639.26 (₱3.2M)
Funding source:
Regular Infra - GAA 2018 Other Infrastructure (CSSP)
Budget year:
2018
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 32668d1caa31… | Apr 30, 2018 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - CAMARINES SUR 5TH | ₱3,156,639.26 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25FD0117 | Nov 14, 2025 | CONSTRUCTION OF BARCELONITA BRIDGE, BRGY. BARCELONITA, CABUSAO, CAMARINES SUR | On-Going | ₱97.4M |
| 25FD0094 | Jul 25, 2025 | CONSTRUCTION OF BARCELONITA, CABUSAO TO MANGGA, SIPOCOT COASTAL ROAD, CAMARINES SUR | On-Going | ₱144.5M |
| 25FD0078 | Jun 20, 2025 | CLUSTER 12: CONSTRUCTION OF RAINWATER COLLECTORS SYSTEM (RWCS), SIPOCOT AND CABUSAO, CAMARINES SUR | On-Going | ₱2.6M |
| 24FD0105 | Jun 16, 2025 | CONSTRUCTION OF 1STY3CL, STA. LUTGARDA NATIONAL HIGH SCHOOL, CABUSAO, CAM. SUR | On-Going | ₱9.8M |
| 25FD0068 | May 28, 2025 | CONSTRUCTION OF ROAD, BIONG, CABUSAO, CAMARINES SUR | On-Going | ₱142.0M |
| 25FD0042 | Mar 27, 2025 | CLUSTER 7: CONSTRUCTION (COMPLETION)/CONSTRUCTION OF MULTI-PURPOSE BUILDING, CABUSAO, CAMARINES SUR | Completed | ₱11.2M |
| 25FD0012 | Feb 17, 2025 | INSTALLATION/APPLICATION OF ROAD SAFETY FACILITIES (ROADWAY LIGHTING) ALONG SIPOCOT-CABUSAO RD - K0394 + (-816) - K0410 + 243, SIPOCOT, CAMARINES SUR | Completed | ₱11.1M |
| 24FD0072 | Jul 15, 2024 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARCELONITA, CABUSAO, CAM. SUR | Completed | ₱8.8M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.