Project 18GA0017
DPWH infrastructure contract
Contract ID:
18GA0017
Fingerprint:
6dcfc292d2ae27…0da761724d Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 26, 2018 (8 yrs 8 mo ago) · Target/actual end Sep 6, 2018
Description:
CONST. OF MULTI-PURPOSE BLDG., BRGY. DAJA NORTE, BANGA,AKLAN
Category:
GAA 2018 LP
Implementing office:
DPWH Aklan DEO · Region VI
Contractor:
A AND M PASTRANA CONST. & SUPPLIES CORPORATION (FORMERLY: PASTRANA CONSTRUCTION & SUPPLIES) · DPWH contractor code 17340
Contract amount:
₱1,920,355.68 (₱1.9M)
Funding source:
Regular Infra - GAA 2018 LP
Budget year:
2018
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 24GA0256 | Aug 7, 2025 | CONTINUING CONSTRUCTION/CONCRETING OF FARM TO MARKET ROAD AT SITIO KALINTAAN, BRGY. DAJA NORTE, BANGA, AKLAN | On-Going | ₱14.9M |
| 24GA0257 | Aug 7, 2025 | CONTINUING CONSTRUCTION/CONCRETING OF FARM TO MARKET ROAD AT BRGY. VENTURANZA TO BRGY. AGBANAWAN TO SITIO TAMPUEAW, BRGY. POLOCATE, BANGA, AKLAN | On-Going | ₱14.9M |
| 25GA0078 | May 23, 2025 | CONSTRUCTION OF ROAD, BARANGAY SIGCAY, BANGA, AKLAN | Completed | ₱4.9M |
| 25GA0079 | May 23, 2025 | CONSTRUCTION OF ROAD, BARANGAY TORRALBA, BANGA, AKLAN | Completed | ₱4.9M |
| 25GA0044 | Apr 3, 2025 | CONSTRUCTION OF ROAD, BARANGAY TABAYON, BANGA, AKLAN | On-Going | ₱4.9M |
| 25G00076 | Mar 24, 2025 | INSTALLATION/APPLICATION OF ROAD SAFETY FACILITIES (ROADWAY LIGHTING) ALONG AKLAN EAST RD- K0286+071- K0290+170 | On-Going | ₱47.8M |
| 24GA0252 | Mar 19, 2025 | CONSTRUCTION OF FLOOD CONTROL PROJECT ALONG AKLAN RIVER, BARANGAY DAJA SUR, BANGA, AKLAN | On-Going | ₱19.2M |
| 25GA0057 | Mar 19, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, SAMPAGUITA STREET, BARANGAY POBLACION, BANGA, AKLAN | On-Going | ₱1.9M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.