Project 18GA0088
DPWH infrastructure contract
Contract ID:
18GA0088
Fingerprint:
fca3d0a5d27fca…80fdddc04a Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jul 20, 2018 (8 yrs 3 mo ago) · Target/actual end Sep 14, 2018
Description:
CONCRETING OF SITIO KABUTONGAN BARANGAY KINALANGAY VIEJO - KINALANGAY NUEVO FMR, BARANGAY KINALANGAY
Category:
Roads
Implementing office:
DPWH Aklan DEO · Region VI
Contractor:
G.F. ROVERO MERCHANDISING · DPWH contractor code 27268
Contract amount:
₱4,824,769.49 (₱4.8M)
Funding source:
Outside Infra - GAA 2018 DA FMR
Budget year:
2018
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 2609e9b020cb… | Jun 28, 2018 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - AKLAN DEO | ₱4,825,118.46 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 24GA0255 | Aug 7, 2025 | CONSTRUCTION OF SUGNOD-SIPAC FMR, BRGY. SUGNOD, MALINAO, AKLAN | On-Going | ₱9.9M |
| 25GA0147 | Aug 7, 2025 | CONSTRUCTION OF RAINWATER COLLECTOR SYSTEM, PROVINCE OF AKLAN | On-Going | ₱2.6M |
| 25GA0120 | Jun 30, 2025 | COMPLETION OF MULTI-PURPOSE BUILDING, BARANGAY BIGA-A, MALINAO, AKLAN | On-Going | ₱1.3M |
| 25GA0087 | Jun 19, 2025 | CONSTRUCTION/COMPLETION OF MULTI-PURPOSE BUILDING, BARANGAY NAVITAS, MALINAO, AKLAN | On-Going | ₱3.0M |
| 25GA0086 | Jun 3, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY BULABUD, MALINAO, AKLAN | On-Going | ₱4.9M |
| 25GA0088 | May 23, 2025 | COMPLETION OF MULTI-PURPOSE BUILDING, BARANGAY KINALANGAY VIEJO, MALINAO, AKLAN | On-Going | ₱3.0M |
| 25GA0129 | May 23, 2025 | CONSTRUCTION OF ROAD, BRGY. SUGNOD, MALINAO, AKLAN | On-Going | ₱4.9M |
| 24GA0247 | Mar 19, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURES ALONG MALINAO RIVER, BARANGAY BANAYBANAY, MALINAO, AKLAN | On-Going | ₱86.0M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.