Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 18GB0118

DPWH infrastructure contract
Contract ID:
18GB0118
Fingerprint:
f7a34d47c0b918…d12abb9ca2 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Apr 24, 2018 (8 yrs 6 mo ago) · Target/actual end Mar 5, 2019
Description:
MULTI-PURPOSE BUILDING/EVACUATION CENTER IN BARBAZA, ANTIQUE
Category:
Buildings and Facilities
Implementing office:
DPWH Antique DEO · Region VI
Contractor:
Contract amount:
₱2,957,427.64 (₱3.0M)
Funding source:
Regular Infra - GAA 2018 LP
Budget year:
2018

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25GB0146Feb 2, 2026CONSTRUCTION OF SCHOOL HEALTH FACILITIES, BARBAZA NHS, BARBAZA, ANTIQUECompleted₱4.2M
25GB0092Jun 20, 2025CONSTRUCTION OF SEA WALL FROM BRGY. GUA TO BRGY. BINANGBANG CENTRO, BARBAZA, ANTIQUEOn-Going₱49.5M
25GB0054Mar 4, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY LISUB, BARBAZA, ANTIQUEOn-Going₱4.9M
25GB0012Feb 21, 2025CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG DALANAS RIVER, BRGY. SAN ANTONIO, BARBAZA, ANTIQUEOn-Going₱144.0M
24GB0123Sep 6, 2024CONCRETING OF SITIO TAWOG, BRGY. ESPARAR FMR BRGY. ESPARAR, BARBAZA, ANTIQUECompleted₱14.9M
24GB0115May 8, 2024CONSTRUCTION OF 1-STOREY 2-CLASSROOM SCHOOL BUILDING IN ESPARAR ELEMENTARY SCHOOL ESPARAR, BARBAZA,Completed₱4.9M
24GB0116May 8, 2024CONSTRUCTION OF 1-STOREY 2-CLASSROOM SCHOOL BUILDING IN BARBAZA CENTRAL SCHOOL POBLACION BARBAZA, ANCompleted₱5.0M
24GB0083Mar 8, 2024CONSTRUCTION OF ROAD, BRGY. TIG-ALARAN-BRGY. LANAS BARBAZA, ANTIQUEOn-Going₱148.5M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.