Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 18GD0102

DPWH infrastructure contract
Contract ID:
18GD0102
Fingerprint:
9eb6438a150c2b…cb70ca29a1 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Dec 9, 2018 (7 yrs 11 mo ago) · Target/actual end Jul 12, 2026
Description:
CONCRETING OF FARM TO MILL ROAD, BRGY. IBACA-BRGY. CUBAY ROAD
Category:
SRA 2018 Farm-to-Mill Roads
Implementing office:
DPWH Capiz 1st DEO · Region VI
Contractor:
NANA BUILDERS · DPWH contractor code 18863
Contract amount:
₱6,412,515.62 (₱6.4M)
Funding source:
Outside Infra - SRA 2018 Farm-to-Mill Roads
Budget year:
2018

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25GD0029Jun 3, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY SANTO NINO, PRESIDENT ROXAS, CAPIZOn-Going₱4.9M
25GD0010Mar 24, 2025CONSTRUCTION OF CONCRETE ROAD - CONSTRUCTION OF ROAD, BARANGAY CULILANG, PRESIDENT ROXAS, CAPIZOn-Going₱4.9M
25GD0013Mar 24, 2025CONSTRUCTION OF CONCRETE ROAD - CONSTRUCTION OF ROAD, BARANGAY VISCAYA, PRESIDENT ROXAS, CAPIZOn-Going₱7.4M
24GD0024Mar 13, 2024CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY HANGLID, PRESIDENT ROXAS, CAPIZCompleted₱4.9M
23GD0076Jun 14, 2023CONSTRUCTION OF MULTI-PURPOSE BUILDING IN BRGY. PANTALAN, PRES. ROXAS, CAPIZCompleted₱7.6M
23GD0074Jun 8, 2023CONCRETING OF BRGY.BADIANGON FMR, BRGY. BADIANGON, PRESIDENT ROXAS, CAPIZOn-Going₱8.7M
23GD0064Apr 28, 2023CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY IBACA, PRESIDENT ROXAS, CAPIZCompleted₱4.1M
23GD0066Apr 28, 2023CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY BADIANGAN, PRESIDENT ROXAS, CAPIZCompleted₱4.9M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.