Project 18GF0037
DPWH infrastructure contract
Contract ID:
18GF0037
Fingerprint:
3785b016f4672a…e2f3461321 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Apr 2, 2018 (8 yrs 7 mo ago) · Target/actual end Nov 20, 2018
Description:
CONCRETING OF MAYANG-NAGBA ROAD, TUBUNGAN, ILOILO
Category:
Roads
Implementing office:
DPWH Iloilo 1st DEO · Region VI
Contractor:
JTA BUILDERS · DPWH contractor code 18401
Contract amount:
₱2,959,991.70 (₱3.0M)
Funding source:
Regular Infra - GAA 2018 LP
Budget year:
2018
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 2446733a2fa5… | Mar 16, 2018 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - ILOILO 1ST DEO | ₱2,959,991.70 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25GF0019 | Jun 3, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING INCLUDING FACILITES, TUBUNGAN, ILOILO | Completed | ₱7.9M |
| 25GF0082 | Apr 11, 2025 | CONSTRUCTION OF ROAD INCLUDING FACILITIES, TUBUNGAN, ILOILO | Completed | ₱27.6M |
| 25GF0002 | Mar 12, 2025 | CONSTRUCTION OF TUBUNGAN FLOOD CONTROL STRUCTURE, TUBUNGAN, ILOILO | Completed | ₱19.5M |
| 24GF0142 | Aug 19, 2024 | CONSTRUCTION OF SCHOOL BUILDING WITH FACILITIES IN CADABDAB ELEMENTARY SCHOOL, CADABDAB, TUBUNGAN, ILOILO | On-Going | ₱47.6M |
| 24GF0106 | May 13, 2024 | REHABILITATION OF TUBUNGAN MULTI-PURPOSE BUILDING, TUBUNGAN, ILOILO | Completed | ₱14.8M |
| 24GF0116 | May 2, 2024 | CONSTRUCTION OF TUBUNGAN RIVER CONTROL STRUCTURE, TUBUNGAN, ILOILO | Completed | ₱19.7M |
| 24GF0103 | Apr 12, 2024 | REHABILITATION OF MULTI-PURPOSE BUILDING, TUBUNGAN, ILOILO | On-Going | ₱8.9M |
| 24GF0112 | Apr 12, 2024 | CONSTRUCTION OF TUBUNGAN ACCESS ROAD, INCLUDING RIVER CONTROL STRUCTURE, TUBUNGAN, ILOILO | On-Going | ₱73.2M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.