Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 18GF0074

DPWH infrastructure contract
Contract ID:
18GF0074
Fingerprint:
88f3d903d1be43…bcda9a701e Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jun 19, 2018 (8 yrs 4 mo ago) · Target/actual end Oct 7, 2018
Description:
CONSTRUCTION OF LANE DIVIDER AND LIGHTINGS ALONG ILOILO-ANTIQUE ROAD (BRGY. RIZAL TUGUISAN,BRGY. GERONA-GIMENO, BRGY. GRIJALVO), GUIMBAL, ILOILO, POBLACION, GUIMBAL, ILOILO (K0027+742.30 - K0028+932.80 WITH EXCEPTION)
Category:
Roads
Implementing office:
DPWH Iloilo 1st DEO · Region VI
Contractor:
NORSAM BUILDERS & CONSTRUCTION SUPPLY · DPWH contractor code 21184
Contract amount:
₱9,758,308.84 (₱9.8M)
Funding source:
Regular Infra - GAA 2018 LP
Budget year:
2018

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
26GF0002May 13, 2026RETROFITTING/STRENGTHENING OF PERMANENT BRIDGES - NABUDUAN BR. (B00149PN) ALONG TIOLAS - SINUGBUHAN RDOn-Going₱5.7M
26GF0021May 13, 2026REHABILITATION/MAJOR REPAIR OF PERMANENT BRIDGES - NITO-AN BR. (B00038PN) ALONG GUIMBAL-IGBARAS-TUBUNGAN-LEON RDOn-Going₱5.7M
25GF0106Jul 28, 2025CONSTRUCTION OF SCHOOL BUILDING, CABASI-STA. ROSA INTEGRATED SCHOOL, ILOILOOn-Going₱9.9M
25GF0107Jul 28, 2025CONSTRUCTION OF SCHOOL BUILDING, NALUNDAN ELEMENTARY SCHOOL, ILOILOOn-Going₱9.9M
25GF0104Jul 7, 2025CONCRETING OF BRGY. TABAT TO AMBARIHON FMR, BRGY. TABAT AND BRGY. AMBARIHON, TUBUNGAN, ILOILOOn-Going₱14.9M
25GF0053Jun 23, 2025CONSTRUCTION OF JARAO RIVER FLOOD CONTROL PROJECT (PHASE 2), BRGY. IGCOCOLO-SIPITAN SECTION, GUIMBAL, ILOILOOn-Going₱48.1M
25GF0011Jun 3, 2025INSTALLATION/APPLICATION OF ROAD SAFETY FACILITIES (ROADWAY LIGHTING) ALONG ILOILO-ANTIQUE RD - K0025+485 - K0027+000On-Going₱19.5M
25GF0084Jun 3, 2025CONSTRUCTION OF JARAO FLOOD CONTROL AND REVETMENT PROJECT ALONG CAMANGAHAN-IGCOCOLO-SIPITAN SECTION, GUIMBAL, ILOILOCompleted₱29.6M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.