Project 18GG0040
DPWH infrastructure contract
Contract ID:
18GG0040
Fingerprint:
a66df342978804…2976893e10 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 20, 2018 (8 yrs 8 mo ago) · Target/actual end Jul 18, 2018
Description:
REHABILITATION OF PAVED ROAD OF MANDURRIAO - SAN MIGUEL - ALIMODIAN - MAASIN - CABATUAN ROAD, K0032 + 889 - K0033 + 120, K0033 + 257.50 - K0033 + 361, K0036 + 609 - K0037 + 276, K0035 + 000 - K0035 + 191, BRGY. MAGSAYSAY, BRGY. BAGACAY WEST & BRGY. MANDOG
Category:
Roads
Implementing office:
DPWH Iloilo 2nd DEO · Region VI
Contractor:
LEGACY CONSTRUCTION CORPORATION (FORMERLY: LEGACY CONSTRUCTION) · DPWH contractor code 22465
Contract amount:
₱25,594,121.00 (₱25.6M)
Funding source:
Regular Infra - GAA 2018 OO-1
Budget year:
2018
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 90f73fac8a54… | Feb 2, 2018 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - ILOILO 2ND DEO | ₱25,594,121.00 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25GR0019 | Jul 7, 2025 | CONSTRUCTION OF FLOOD CONTROL/SLOPE PROTECTION ALONG TIGUM RIVER, MAASIN ILOILO | On-Going | ₱39.1M |
| 25GG0062 | Jul 4, 2025 | CONSTRUCTION (COMPLETION) OF MULTI - PURPOSE BUILDING, BARANGAY CANAWILI, MAASIN, ILOILO | Completed | ₱3.5M |
| 25GG0063 | Jul 4, 2025 | CONSTRUCTION (COMPLETION) OF MULTI - PURPOSE BUILDING, BARANGAY UBIAN, MAASIN, ILOILO | Completed | ₱3.9M |
| 25GG0100 | Jul 4, 2025 | CONSTRUCTION (COMPLETION) OF MULTI - PURPOSE BUILDING, BARANGAY MAGSAYSAY, MAASIN, ILOILO | On-Going | ₱2.7M |
| 25GG0146 | Jul 4, 2025 | CONSTRUCTION OF ROAD, BARANGAY BULAY, MAASIN, ILOILO | Completed | ₱4.9M |
| 25GG0152 | Jul 4, 2025 | CONSTRUCTION OF MULTI - PURPOSE BUILDING, MAASIN, ILOILO | On-Going | ₱9.9M |
| 25GG0019 | Jul 3, 2025 | CONSTRUCTION (COMPLETION) OF MULTI - PURPOSE BUILDING, BARANGAY DALUSAN, MAASIN, ILOILO | Completed | ₱3.5M |
| 25GG0020 | Jul 3, 2025 | CONSTRUCTION (COMPLETION) OF MULTI - PURPOSE BUILDING, BARANGAY SINUBSUBAN, MAASIN, ILOILO | Completed | ₱2.9M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.