Project 18GG0092
DPWH infrastructure contract
Contract ID:
18GG0092
Fingerprint:
ea863b5cc8004c…8860708181 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Apr 25, 2018 (8 yrs 6 mo ago) · Target/actual end Aug 22, 2018
Description:
CONSTRUCTION OF MULTI-PURPOSE BUILDING (GYM), ANILAO, ILOILO
Category:
Buildings and Facilities
Implementing office:
DPWH Iloilo 2nd DEO · Region VI
Contractor:
PITONG BUILDERS & CONSTRUCTION SUPPLY, INC. (FORMERLY: PITONG BUILDERS & CONSTRUCTION SUPPLY) · DPWH contractor code 39273
Contract amount:
₱7,835,835.43 (₱7.8M)
Funding source:
Regular Infra - GAA 2018 LP
Budget year:
2018
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 26GG0049 | Jun 9, 2026 | ROAD WIDENING - ANILAO BY-PASS ROAD, BARANGAY SAMBAG CULOB - BARANGAY SANTA RITA, ANILAO, ILOILO - STA. 0 + 140 - STA. 1 + 340 | On-Going | ₱46.3M |
| 25GG0027 | May 21, 2025 | CONSTRUCTION OF ROAD, BARANGAY POBLACION CULOB - BALABAG, ANILAO, ILOILO | Completed | ₱6.9M |
| 25GG0204 | Mar 24, 2025 | CONCRETING OF BRGY. SAMBAG CULOB TO BRGY. AGBATUAN FMR, BRGY. SAMBAG CULOB TO BRGY. AGBATUAN, ANILAO, ILOILO | Completed | ₱14.9M |
| 25GG0206 | Mar 24, 2025 | CONCRETING OF BRGY. CAG-AN FMR, BRGY. NCAG-AN, ANILAO, ILOILO | Completed | ₱14.9M |
| 25GG0105 | Mar 21, 2025 | CONSTRUCTION OF CONCRETE ROAD - ANILAO BYPASS ROAD | On-Going | ₱29.3M |
| 25GG0176 | Mar 21, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, PHASE III, BARANGAY POBLACION, ANILAO, ILOILO | On-Going | ₱24.7M |
| 25GG0178 | Mar 7, 2025 | CONSTRUCTION OF MULTI - PURPOSE BUILDING, PHASE II, ANILAO, ILOILO | On-Going | ₱19.9M |
| 25GG0133 | Mar 6, 2025 | CONSTRUCTION OF MULTI - PURPOSE BUILDING, PHASE 1, ANILAO, ILOILO | On-Going | ₱12.8M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.