Project 18GG0119
DPWH infrastructure contract
Contract ID:
18GG0119
Fingerprint:
de7fd13271defc…97797a69ef Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start May 21, 2018 (8 yrs 5 mo ago) · Target/actual end Jul 1, 2018
Description:
CONCRETING OF BRGY. MERCED - BRGY. CARMELO FMR, BANATE, ILOILO
Category:
Roads
Implementing office:
DPWH Iloilo 2nd DEO · Region VI
Contractor:
A.D. PENDON CONSTRUCTION & SUPPLY, INC. (FORMERLY: ADP CONSTRUCTION & SUPPLY) · DPWH contractor code 3466
Contract amount:
₱4,873,608.63 (₱4.9M)
Funding source:
Outside Infra - GAA 2018 DA FMR
Budget year:
2018
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25GG0061 | May 21, 2025 | CONSTRUCTION (COMPLETION) OF MULTI - PURPOSE BUILDING, BARANGAY BULARAN, BANATE, ILOILO | Completed | ₱4.9M |
| 25GG0119 | Mar 21, 2025 | CONSTRUCTION (COMPLETION) OF ROAD, BARANGAY TALUCDANGAN, BANATE, ILOILO | Completed | ₱2.0M |
| 25GG0120 | Mar 21, 2025 | CONSTRUCTION (COMPLETION) OF ROAD, BARANGAY LIBERTAD, BANATE, ILOILO | Completed | ₱2.4M |
| 25GG0124 | Mar 21, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY POBLACION, BANATE, ILOILO | Completed | ₱9.8M |
| 25GG0131 | Mar 21, 2025 | CONSTRUCTION (COMPLETION) OF ROAD, BARANGAY BUBON, BANATE, ILOILO | Completed | ₱1.9M |
| 25GG0136 | Mar 21, 2025 | CONSTRUCTION (COMPLETION) OF MULTI - PURPOSE BUILDING, BARANGAY CARMELO, BANATE, ILOILO | Completed | ₱2.5M |
| 25GG0154 | Mar 21, 2025 | CONSTRUCTION (COMPLETION) OF MULTI - PURPOSE BUILDING, BRGY. POBLACION, BANATE, ILOILO | Completed | ₱2.0M |
| 25GG0155 | Mar 21, 2025 | CONSTRUCTION (COMPLETION) OF MULTI - PURPOSE BUILDING, BARANGAY BELEN, BANATE, ILOILO | Completed | ₱2.0M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.