Project 18GH0165
DPWH infrastructure contract
Contract ID:
18GH0165
Fingerprint:
dbe70253f3b593…69248691d8 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jan 3, 2019 (7 yrs 10 mo ago) · Target/actual end May 26, 2019
Description:
CONSTRUCTION OF MODIFIED STANDARD DPWH - DEPED ONE (1) UNIT TWO (2) STOREY TWO (2) REGULAR WORKSHOP BUILDING, DON CASIMERO ANDRADA NHS, CARLES, ILOILO
Category:
Buildings and Facilities
Implementing office:
DPWH Iloilo 3rd DEO · Region VI
Contractor:
VIRGIN BUILDERS CONSTRUCTION · DPWH contractor code 36201
Contract amount:
₱10,810,021.78 (₱10.8M)
Funding source:
Outside Infra - GAA 2018 DepEd BEFF
Budget year:
2018
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 9d3e2198a3f7… | Dec 19, 2018 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - ILOILO 3RD DEO | ₱10,810,021.78 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25GH0153 | May 26, 2025 | CONSTRUCTION OF ABC BUILDING AT BARANGAY POBLACION, CARLES, ILOILO | Completed | ₱4.9M |
| 25GH0016 | Mar 26, 2025 | CONSTRUCTION (COMPLETION) OF MULTI- PURPOSE BUILDING, BARANGAY CABILAO GRANDE, CARLES, ILOILO | Completed | ₱2.0M |
| 25GH0042 | Mar 26, 2025 | CONSTRUCTION OF CONCRETE ROAD- CONSTRUCTION OF ROAD, BARANGAY NALUMSAN, CARLES, ILOILO | Completed | ₱4.9M |
| 25GH0104 | Mar 25, 2025 | CONSTRUCTION OF CONCRETE ROAD- CONSTRUCTION OF ROAD, BARANGAY GUINTICGAN, CARLES, ILOILO | On-Going | ₱9.7M |
| 25GH0111 | Mar 25, 2025 | CONSTRUCTION OF CONCRETE ROAD- CONSTRUCTION OF ROAD, BARANGAY BAROSBOS, CARLES, ILOILO | Completed | ₱9.8M |
| 25GH0093 | Mar 24, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY GUINTICGAN, CARLES, ILOILO | Completed | ₱3.9M |
| 25GH0013 | Feb 17, 2025 | CONSTRUCTION (COMPLETION) OF MULTI- PURPOSE BUILDING, BARANGAY POBLACION, CARLES, ILOILO | Completed | ₱3.0M |
| 25GH0015 | Feb 17, 2025 | CONSTRUCTION (COMPLETION) OF MULTI- PURPOSE BUILDING, BARANGAY TUPAZ, CARLES, ILOILO | Completed | ₱3.0M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.