Project 18HA0078
DPWH infrastructure contract
Contract ID:
18HA0078
Fingerprint:
bac5fad05dc2d7…2412bbb71f Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jun 29, 2018 (8 yrs 4 mo ago) · Target/actual end Nov 25, 2018
Description:
CONSTRUCTION OF WATER SUPPLY LEVEL III, BARANGAY POBLACION-ALEGRIA-CANDUMAYAO-BAANG-LIBORON-TRIPLE UNION, CATIGBIAN, BOHOL
Category:
Water Provision and Storage
Implementing office:
DPWH Bohol 1st DEO · Region VII
Contractor:
BNYU DEVELOPMENT CORPORATION · DPWH contractor code 27725
As listed: BNYU DEVELOPMENT CORPORATION (FORMERLY:BNYU ENTERPRISES & CONSTRUCTION)
Contract amount:
₱10,419,443.72 (₱10.4M)
Funding source:
Regular Infra - GAA 2018 LP
Budget year:
2018
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| de34c2b86e39… | Jun 14, 2018 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - BOHOL 1ST ED | ₱10,419,443.72 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25HA0087 | Jun 2, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, AMBUAN, CATIGBIAN, BOHOL | Completed | ₱4.9M |
| 25HA0088 | Jun 2, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, CAMBAILAN, CATIGBIAN, BOHOL | Completed | ₱4.9M |
| 25HA0089 | Jun 2, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, KANG-IRAS, CATIGBIAN, BOHOL | Completed | ₱4.9M |
| 25HA0090 | Jun 2, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, MAITUM, CATIGBIAN, BOHOL | Completed | ₱4.9M |
| 25HA0091 | Jun 2, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, LIBORON, CATIGBIAN, BOHOL | Completed | ₱4.9M |
| 25HA0106 | Jun 2, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, CAUSWAGAN NORTE, CATIGBIAN, BOHOL | Completed | ₱4.8M |
| 25HA0107 | Jun 2, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, CANDUMAYAO, CATIGBIAN, BOHOL | Completed | ₱4.8M |
| 25HA0108 | Jun 2, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BONGBONG, CATIGBIAN, BOHOL | Completed | ₱4.9M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.