Project 18HF0210

DPWH infrastructure contract
Contract ID:
18HF0210
Fingerprint:
ac51c89198aa0d…6eb3bbb6cb Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Dec 25, 2019 (6 yrs 10 mo ago) · Target/actual end Feb 21, 2020
Description:
COMPLETION OF ALOGUINSAN RURAL HEALTH UNIT, POBLACION, ALOGUINSAN, CEBU
Category:
Buildings and Facilities
Implementing office:
DPWH Cebu 3rd DEO · Region VII
Contract amount:
₱2,910,803.29 (₱2.9M)
Funding source:
Outside Infra - GAA 2018 DOH HFEP
Budget year:
2018

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
26RB0044Jun 24, 2026PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY -VALLEHERMOSO-CANLAON CITY-LA CASTELLANA RD - K0085 + 000 - K0087 + 242On-Going₱51.5M
25RB0011Feb 26, 2026REPAIR/REHABILITATION OF CLASSROOMS, CAMP CLARK ES, ISABELA, NEGROS OCCIDENTAL (SCHOOL ID : 117201)Completed₱7.5M
25GL0041Jun 17, 2025ROAD CONCRETING AT BARANGAY SAN AGUSTIN, ISABELA, NEGROS OCCIDENTALCompleted₱9.8M
25GL0047Jun 17, 2025ROAD CONCRETING AT BARANGAY INOLINGAN, MOISES PADILLA, NEGROS OCCIDENTALOn-Going₱10.3M
25GL0092Jun 17, 2025CONSTRUCTION OF BINALBAGAN RIVER BANK SLOPE PROTECTION (DOWNSTREAM OF BINALBAGAN BAGACAY BRIDGE) ALONG HINIGARAN -ISABELA RD, LEFT BANK, STA 18+687.6 - 18+837.6, NEGROS OCCIDENTALOn-Going₱99.0M
25GL0093Jun 17, 2025CONSTRUCTION OF BINALBAGAN RIVER BANK SLOPE PROTECTION (DOWNSTREAM OF ALICANTE BRIDGE) ALONG JCT BAGONAWA - LA CASTELLANA - ISABELA RD, LEFT BANK, STA 30+030 - 30+180, NEGROS OCCIDENTALOn-Going₱99.0M
25GL0094Jun 17, 2025CONSTRUCTION OF GUINTUBHAN RIVER BANK CONCRETE SLOPE PROTECTION, BARANGAY MASABLAY, ISABELA, NEGROS OCCIDENTALOn-Going₱48.2M
25GL0071Jun 5, 2025CONSTRUCTION OF ROAD, BARANGAY TINONGAN TO BARANGAY SAN AGUSTIN, ISABELA, NEGROS OCCIDENTALCompleted₱9.9M