Project 18HG0099
DPWH infrastructure contract
Contract ID:
18HG0099
Fingerprint:
aaa21c8f5562d7…712035cf3d Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 13, 2018 (8 yrs 9 mo ago) · Target/actual end Aug 15, 2018
Description:
ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM; REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADS - N. BACALSO AVENUE (CEBU SOUTH ROAD), SECTION 1: K0091+000 - K0093+000
Category:
GAA 2018 OO-1
Implementing office:
DPWH Cebu 2nd DEO · Region VII
Contractor:
APRIL ROSE ENT. & BUILDERS (42590) / QM BUILDERS · DPWH contractor code 30743
Contract amount:
₱55,164,728.52 (₱55.2M)
Funding source:
Regular Infra - GAA 2018 OO-1
Budget year:
2018
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25HE0129 | Oct 21, 2025 | CONCRETING OF SITIO ABACA, BRGY. NUG-AS FMR, BRGY. NUG-AS, ALCOY, CEBU | On-Going | ₱25.1M |
| 25HE0094 | May 29, 2025 | CONCRETING OF BRGY. EL PARDO FMR, BRGY. EL PARDO, BOLJOON, CEBU | On-Going | ₱14.6M |
| 25HE0036 | Mar 13, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY NUG-AS, ALCOY, CEBU | On-Going | ₱2.0M |
| 24HG0095 | Jul 15, 2024 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY POBLACION, ALCOY, CEBU | On-Going | ₱4.9M |
| 24HG0096 | Jul 15, 2024 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING, POBLACION, ALCOY, CEBU | On-Going | ₱4.9M |
| 24HG0075 | May 30, 2024 | CONCRETING OF SITIO ABACA, BRGY. NUG-AS FMR, BRGY. NUG-AS, ALCOY, CEBU | On-Going | ₱14.8M |
| 24HG0069 | May 15, 2024 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - IMPROVEMENT OF BARANGAY EL PARDO-BARANGAY NANGKA ROAD, BOLJOON, CEB | Completed | ₱4.9M |
| 24HG0049 | Mar 19, 2024 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD, SITIO MALARID OF BRGY. NUG-AS BARANGAY ROAD, | Completed | ₱4.9M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.