Project 18HI0002
DPWH infrastructure contract
Contract ID:
18HI0002
Fingerprint:
b52a276a140870…09e244fc49 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start May 7, 2018 (8 yrs 6 mo ago) · Target/actual end Nov 2, 2018
Description:
OFF- CARRIAGEWAY IMPROVEMENT :SHOULDER PAVING/CONSTRUCTION - CEBU NORTH HAGNAYA WHARF ROAD, K0043+000 - K0044+560, K0046+918 - K0047+668, K0055+725 - K0056+840, K0070+725 - K0071+615, K0073+687 - K0073+771, K0073+822 - K0073+847,CARMEN, CATMON AND BORBON,
Category:
Roads
Implementing office:
DPWH Cebu 5th DEO · Region VII
Contractor:
VEN RAY CONSTRUCTION CORPORATION · DPWH contractor code 18310
Contract amount:
₱64,258,257.00 (₱64.3M)
Funding source:
Regular Infra - GAA 2018 OO-1
Budget year:
2018
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 26HI0013 | Jun 24, 2026 | ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - SECONDARY ROADS - CEBU NORTH HAGNAYA WHARF RD - K0068+000 - K0069+000, K0071+615 - K0 | On-Going | ₱68.2M |
| 25HI0099 | Jul 14, 2025 | CSSP: SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF MATINAO-BUNDO-BILI-CAJEL ROAD, BORBON, CEBU | On-Going | ₱38.4M |
| 25HI0095 | Jun 26, 2025 | CONCRETING OF BRGY. MANAGASE FMR, BRGY. MANAGASE, BORBON, CEBU | On-Going | ₱14.6M |
| 25HI0008 | Mar 18, 2025 | CSSP: SPECIAL ROAD FUND - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239 - REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - SECONDARY ROADS ALONG CEBU NORTH HAGNAYA WHARF RD - K0052 + 000 - K0052 + 182, K0075 + 000 - K0075 + 430 | Completed | ₱21.0M |
| 24H00164 | Mar 3, 2025 | CONSTRUCTION/COMPLETION OF ACADEMIC BUILDINGS, CEBU TECHNOLOGICAL UNIVERSITY (CTU) - BORBON CAMPUS - CEBU TECHNOLOGICAL UNIVERSITY | On-Going | ₱49.7M |
| 24HI0155 | Feb 28, 2025 | CSSP: SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BLDGS/FACILITIES - CONST/COMPLETION OF FLOOD CONTROL STRUCTURE (STORM SURGE PROTECTION) INCLUDING FACILITIES, POB., BORBON, | Completed | ₱57.9M |
| 25HI0050 | Feb 20, 2025 | CSSP: BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTIPURPOSE BUILDINGS / FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY TABUNAN, BORBON, CEBU | Completed | ₱2.0M |
| 25HI0011 | Feb 19, 2025 | CSSP: BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES- CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY TAGNUCAN, BORBON, CEBU | Completed | ₱3.0M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.