Project 18IA0006
DPWH infrastructure contract
Contract ID:
18IA0006
Fingerprint:
f8237c6ccf364c…03a8f67a75 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 18, 2018 (8 yrs 8 mo ago) · Target/actual end Aug 16, 2018
Description:
CONST./EXTENSION OF FLOOD CONTROL STRUCTURE ALONG MOOG RIVER PROTECTING MOOG BRIDGE AND BILIRAN CIRCUMFERENTIAL ROAD, LEFTSIDE (11.4878, 124.4494); RIGHTSIDE (11.4881, 124.44963), BILIRAN, PROVINCE OF BILIRAN
Category:
Flood Control and Drainage
Implementing office:
DPWH Biliran DEO · Region VIII
Contractor:
REX E. MORALES CONSTRUCTION · DPWH contractor code 17427
Contract amount:
₱28,048,033.81 (₱28.0M)
Funding source:
Regular Infra - GAA 2018 OO-2
Budget year:
2018
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 97949aac7ddc… | Feb 6, 2018 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - BILIRAN ED | ₱28,048,033.81 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 26IA0002 | Jun 23, 2026 | REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPS AND LANDSLIDE - SECONDARY ROADS - BILIRAN CIRCUMFERENTIAL RD - K1012+852 - K1013+083, K1013+839-K1014+009, K1014+603 - K1014+683, K1014+869 - K1014+991 | On-Going | ₱37.9M |
| 25IA0171 | Jan 28, 2026 | REPAIR/REHABILITATION OF CLASSROOMS, BUSALI ES, BILIRAN, BILIRAN | On-Going | ₱3.2M |
| 25IA0161 | Jul 15, 2025 | REHABILITATION OF ROAD, BARANGAY BUSALI, BILIRAN, BILIRAN | On-Going | ₱9.8M |
| 24IA0151 | Apr 10, 2025 | CONCRETING OF FMR- BRGY. PINANGUMHAN, BILIRAN TO BRGY. HAGUIKHIKAN, NAVAL, BILIRAN | On-Going | ₱29.8M |
| 25IA0097 | Mar 25, 2025 | INSTALLATION/APPLICATION OF ROAD SAFETY FACILITIES - BILIRAN CIRCUMFERENTIAL RD. - K1012+150 - K1016+650 | Completed | ₱29.4M |
| 25IA0029 | Feb 28, 2025 | NETWORK DEVELOPMENT - ROAD WIDENING - SECONDARY ROADS - BILIRAN CIRCUMFERENTIAL RD, K1109+364-K1110+542 | On-Going | ₱48.9M |
| 25IA0006 | Feb 26, 2025 | CONSTRUCTION OF SANTOL FLOOD CONTROL STRUCTURE ALONG BILIRAN CIRCUMFERENTIAL ROAD, BILIRAN, BILIRAN | On-Going | ₱48.9M |
| 25IA0018 | Feb 26, 2025 | CONSTRUCTION OF ROAD, BARANGAY BUSALI, BILIRAN, BILIRAN | Completed | ₱14.6M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.