Project 18IA0030
DPWH infrastructure contract
Contract ID:
18IA0030
Fingerprint:
b6871c274097aa…fa19af10d8 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 20, 2018 (8 yrs 8 mo ago) · Target/actual end Jul 21, 2018
Description:
CONSTRUCTION/EXTENSION OF FLOOD CONTROL STRUCTURE ALONG BANLAS RIVER PROTECTING BANLAS BRIDGE AND MARIPIPI CIRCUMFERENTIAL ROAD, MARIPIPI (11.8024, 124.3488), MARIPIPI, PROVINCE OF BILIRAN
Category:
Flood Control and Drainage
Implementing office:
DPWH Biliran DEO · Region VIII
Contractor:
YOYEN ENTERPRISES · DPWH contractor code 15541
Contract amount:
₱13,835,000.00 (₱13.8M)
Funding source:
Regular Infra - GAA 2018 OO-2
Budget year:
2018
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 1da05f585538… | Feb 8, 2018 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - BILIRAN ED | ₱13,835,000.00 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25IA0144 | Jun 19, 2025 | CONSTRUCTION OF A MULTI-PURPOSE BUILDING (MUSEUM) IN MARIPIPI, BILIRAN | Completed | ₱4.9M |
| 25IA0086 | May 27, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY OL-OG, MARIPIPI, BILIRAN | Completed | ₱4.9M |
| 25IA0116 | May 27, 2025 | COMPLETION OF MULTI-PURPOSE BUILDING, BARANGAY TRABUGAN, MARIPIPI, BILIRAN | Completed | ₱2.0M |
| 25IA0092 | Feb 27, 2025 | REHABILITATION OF ROAD, BARANGAY BINONGTO-AN, MARIPIPI, BILIRAN | On-Going | ₱5.9M |
| 25IA0065 | Feb 26, 2025 | CONSTRUCTION OF SEAWALL, BARANGAY ERMITA, MARIPIPI, BILIRAN | Completed | ₱4.9M |
| 25IA0079 | Feb 26, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, COVERED COURT, BARANGAY ERMITA, MARIPIPI, BILIRAN | Completed | ₱2.0M |
| 25IA0100 | Feb 26, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, LEGISLATIVE BUILDING, PHASE 3, BARANGAY ERMITA, MARIPIPI, BILIRAN | Completed | ₱4.9M |
| 24IA0068 | Jul 9, 2024 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, PHASE 2, BARANGAY BINALAYAN WEST, MARIPIPI, BILIRAN | On-Going | ₱6.1M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.