FY2026 GAA: ₱6.79T
PisoScan

Project 18IB0132

DPWH infrastructure contract
Contract ID:
18IB0132
Fingerprint:
c746ce6deee8d9…1856bb69c8 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jun 28, 2018 (8 yrs 4 mo ago) · Target/actual end Oct 20, 2018
Description:
CONSTRUCTION OF 1-STOREY, 2- CL. RM. SCHOOL BUILDING AT DAO INTEGRATED SCHOOL, ORAS, EASTERN SAMAR
Category:
Buildings and Facilities
Implementing office:
DPWH Eastern Samar DEO · Region VIII
Contractor:
TUBIGAN BUILDERS · DPWH contractor code 33185
Contract amount:
₱3,024,767.93 (₱3.0M)
Funding source:
Outside Infra - GAA 2018 DepEd BEFF
Budget year:
2018

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
bcda75c87820…Jun 11, 2018DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - EASTERN SAMAR DEO₱2,911,695.11

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25IB0174Dec 8, 2025CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY CAMANGA, ORAS, EASTERN SAMAROn-Going₱4.9M
25IB0156Nov 12, 2025CONSTRUCTION OF ROAD, BARANGAY JAPAY, ORAS, EASTERN SAMAROn-Going₱4.9M
25IB0142Aug 26, 2025CONSTRUCTION OF BRIDGE, BARANGAY RIZAL, ORAS, EASTERN SAMARCompleted₱4.9M
25IB0073Jul 30, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY HALL, BARANGAY TAWAGAN, ORAS, EASTERN SAMARCompleted₱4.9M
25IB0051Jun 3, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY GAMOT, ORAS, EASTERN SAMARCompleted₱4.9M
25IB0074Jun 3, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, SENIOR CITIZEN CENTER, BARANGAY SAN ROQUE, ORAS, EASTERN SAMARCompleted₱4.9M
25IB0093Jun 3, 2025CONSTRUCTION OF EVACUATION CENTER, BARANGAY MALINGON, ORAS, EASTERN SAMARCompleted₱4.9M
25IB0010Feb 25, 2025PREVENTIVE MAINTENANCE SECONDARY ROADS, JCT. TAFT-ORAS-SAN POLICARPO-ARTECHE ROAD, K0914+249 - K0914+334, K0914+488 - K0914+534, K0915+532 - K0915+550, K0915+588 - K0915+605, K0915+597 - K0915+617, K0916+168 - K0916+186, K0916+511 - K0916+530, K0916+552 -Completed₱5.1M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.