Project 18IC0055
DPWH infrastructure contract
Contract ID:
18IC0055
Fingerprint:
6181559b4d92d1…56a1fe6609 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Sep 3, 2018 (8 yrs 2 mo ago) · Target/actual end Jan 18, 2019
Description:
CONST./REHAB./IMPROVEMENT OF FLOOD CONTROL PROJECT ALONG LIMBUHAN RIVER, CHAINAGE 1090 - CHAINAGE 1230, TANAUAN, LEYTE
Category:
Flood Control and Drainage
Implementing office:
DPWH Leyte 1st DEO · Region VIII
Contractor:
FERDSTAR BUILDERS INC. · DPWH contractor code 4965
Contract amount:
₱18,610,736.04 (₱18.6M)
Funding source:
Regular Infra - GAA 2018 OO-2
Budget year:
2018
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25IC0098 | Oct 9, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BANTAY DAGAT HEADQUARTERS, BARANGAY STO. NIÑO, TANAUAN, LEYTE | On-Going | ₱6.7M |
| 25IC0140 | Sep 17, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY GUINDAG-AN, TANAUAN, LEYTE | On-Going | ₱4.9M |
| 25IC0116 | Sep 12, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY CANBALISARA, TANAUAN, LEYTE | On-Going | ₱4.9M |
| 24IC0220 | Aug 26, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY SAN VICTOR, TANAUAN, LEYTE | Completed | ₱6.4M |
| 25IC0145 | Aug 14, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY LINAO, TANAUAN, LEYTE | Completed | ₱4.9M |
| 25IC0200 | Aug 14, 2025 | CONCRETING OF BRGY. BINONGTO-AN TO BRGY. MALAGUICAY FMR, BRGY. BINONGTO-AN AND BRGY. MALAGUICAY, TANAUAN, LEYTE | On-Going | ₱21.9M |
| 24IC0225 | Jul 17, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY SAN VICENTE, TOLOSA, LEYTE | On-Going | ₱48.2M |
| 25IC0075 | Jul 17, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY OLOT, TOLOSA, LEYTE | On-Going | ₱96.5M |