Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 18IG0068

DPWH infrastructure contract
Contract ID:
18IG0068
Fingerprint:
5c46ec58f43a0c…8c0cc6bcf6 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jun 4, 2018 (8 yrs 5 mo ago) · Target/actual end Jan 26, 2019
Description:
WIDENING OF PERMANENT BRIDGES, SOLOKEGUE BR. (B00534LT) ALONG DAANG MAHARLIKA (LT), JAVIER, LEYTE
Category:
Bridges
Implementing office:
DPWH Leyte 5th DEO · Region VIII
Contractor:
FAIRCHILD BUILDERS & DEVELOPERS, INC. · DPWH contractor code 10024
Contract amount:
₱16,267,662.95 (₱16.3M)
Funding source:
Regular Infra - GAA 2018 OO-1
Budget year:
2018

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
9af0840111a1…May 22, 2018DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - LEYTE 5TH ED₱15,272,168.88

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25IG0021Jun 3, 2025CONSTRUCTION OF ROAD, BARANGAY SAN SOTERO, JAVIER, LEYTECompleted₱4.9M
25IG0032May 20, 2025NETWORK DEVELOPMENT - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - JAVIER BY-PASS ROAD, LEYTECompleted₱19.6M
25IG0056May 20, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY BINULHO, JAVIER, LEYTECompleted₱3.0M
25I00014Apr 10, 2025ASSET PRESERVATION - PREVENTIVE MAINTENANCE - PRIMARY ROADS - MAHARLIKA HIGHWAY - K0961+530 - K0961+673, LEYTE 5TH LDOn-Going₱8.5M
25I00023Apr 10, 2025ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - PRIMARY ROADS - MAHARLIKA HIGHWAY - K0963+902 - K0964+979, LEYTE 5TH LDOn-Going₱52.3M
25IG0011Mar 27, 2025NETWORK DEVELOPMENT - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - ABUYOG BY-PASS ROAD, LEYTECompleted₱49.0M
25IG0002Mar 11, 2025CONSTRUCTION OF ROAD, BARANGAY ANDRES BONIFACIO, JAVIER, LEYTECompleted₱4.9M
25IG0015Mar 11, 2025CONSTRUCTION OF ROAD, BARANGAY PINOCAWAN, JAVIER, LEYTECompleted₱4.9M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.