Physical progress:
100%
Timeline:
Start May 8, 2018 (8 yrs 6 mo ago) · Target/actual end Jan 17, 2019
Description:
REPAIR/REHABILILITAATION OF SLOPE PROTECTION WITH SLIP ALONG LANAO-PAGADIAN-ZAMBOANGA CITY ROAD, BASALEM SECTION, BUUG, ZAMBOANGA SIBUGAY, K1724+150+K1724+160, K1724+180-K1724+210, K1724+240-K1724+270,K1725+670-K1725+710
Category:
Flood Control: Construction - Slope Protection using Structural Measures (e.g., Revetment, Retaining Structures, Rock Netting, Concrete Crib, Shotcrete, MSE Walls, Gabions, Riprap, Masonry), Roads: Construction - Slope Protection using Structural Measures (e.g. Revetment, Retaining Structures, Rock Netting, Concrete Crib, Shotcrete, MSE Walls, Gabions, Riprap, Masonry)
Implementing office:
DPWH Zamboanga Sibugay 1st DEO · Region IX
Contractor:
BADSBRO CONSTRUCTION AND GENERAL MERCHANDISE (32876) / RCDG CONSTRUCTION CORPORATION · DPWH contractor code 5063
Contract amount:
₱49,000,000.00 (₱49.0M)
Funding source:
Regular Infra - Flood Control: Construction - Slope Protection using Structural Measures (e.g., Revetment, Retaining Structures, Rock Netting, Concrete Crib, Shotcrete, MSE Walls, Gabions, Riprap, Masonry), Roads: Construction - Slope Protection using Structural Measures (e.g. Revetment, Retaining Structures, Rock Netting, Concrete Crib, Shotcrete, MSE Walls, Gabions, Riprap, Masonry)
Budget year:
2018
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25J00057 | Jul 23, 2025 | ROAD WIDENING - PRIMARY ROADS - MAHARLIKA HIGHWAY (PAGADIAN CITY - ZAMBOANGA CITY RD) | On-Going | ₱90.9M |
| 25J00062 | Jul 23, 2025 | ROAD WIDENING- PRIMARY ROADS- MAHARLIKA HIGHWAY (LANAO- PAGADIAN - ZAMBOANGA CITY RD) | On-Going | ₱159.3M |
| 25J00024 | Mar 19, 2025 | PREVENTIVE MAINTENANCE - PRIMARY ROADS, MAHARLIKA HIGHWAY (PAGADIAN CITY - ZAMBOANGA CITY RD) K1711+000.00 - K1712+810.00, K1712+810 - K 1712+834.00 | On-Going | ₱96.0M |
| 25J00128 | Mar 14, 2025 | CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT BOGAYO RIVER, KUMALARANG BR. 1 SECTION (B00549MN) ALONG PAGADIAN CITY-ZAMBOANGA CITY RD (S01453MN), PACKAGE 2, BARANGAY BOGAYO, KUMA | On-Going | ₱142.6M |
| 25JG0002 | Feb 19, 2025 | NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS ALONG NRJ-BOGAYO-KITAAN DAGAT-MAHAYAHAY ROAD, (PHASE IV), KUMALARANG, ZAMBOANGA DEL SUR | On-Going | ₱24.4M |
| 25JG0003 | Feb 19, 2025 | NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS ALONG SAN ISIDRO - PANGI DIVERSION ROAD, SAN ISIDRO, BAYOG, ZAMBOANGA DEL SUR | Completed | ₱24.5M |
| 25JG0015 | Feb 19, 2025 | ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD, BARANGAY GAWIL TO BARANGAY BOLISONG, KUMALARANG, ZAMBOANGA DEL SUR | Completed | ₱49.0M |
| 24JG0040 | Jul 12, 2024 | CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF KUMALARANG RIVER FLOOD CONTROL STRUCTURE ALONG IMELDA-BAYOG-KUMALARANG-LAPUYAN-MARGOSATUBIG RD S01513MN, BESIDE KUMALARANG BRIDGE 3 | Completed | ₱77.1M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.