Project 18JI0086
DPWH infrastructure contract
Contract ID:
18JI0086
Fingerprint:
6de6a3da877780…b9313c4d32 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Sep 16, 2018 (8 yrs 1 mo ago) · Target/actual end May 20, 2019
Description:
CONSTRUCTION OF TWO(2) STOREY TWELVE(12) CLASSROOM SCHOOL BUILDING AT MABUHAY CES, MABUHAY, ZAMBOANGA SIBUGAY
Category:
Buildings and Facilities
Implementing office:
DPWH Zamboanga Sibugay 1st DEO · Region IX
Contractor:
E.G. AYOMA CONSTRUCTION AND ENTERPRISES · DPWH contractor code 39874
Contract amount:
₱23,877,904.99 (₱23.9M)
Funding source:
Outside Infra - GAA 2018 DepEd BEFF
Budget year:
2018
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 867f7eea5710… | Aug 24, 2018 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - ZAMBOANGA SIBUGAY | ₱23,877,904.99 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25JI0040 | Jul 11, 2025 | CONSTRUCTION OF MULTI PURPOSE BUILDING, STO. NIÑO, MABUHAY, ZAMBOANGA SIBUGAY | On-Going | ₱4.9M |
| 25JI0041 | Jul 11, 2025 | CONSTRUCTION OF MULTI PURPOSE BUILDING, BAGONG SILANG, MABUHAY, ZAMBOANGA SIBUGAY | Completed | ₱4.9M |
| 25JI0042 | Jul 11, 2025 | COMPLETION OF MULTI PURPOSE BUILDING, ABUNDA, MABUHAY, ZAMBOANGA SIBUGAY | On-Going | ₱4.9M |
| 25JI0075 | Jul 11, 2025 | COMPLETION OF MULTI PURPOSE BUILDING, TAGUISIAN, MABUHAY, ZAMBOANGA SIBUGAY | On-Going | ₱3.0M |
| 25JI0076 | Jul 11, 2025 | COMPLETION OF MULTI PURPOSE BUILDING, CALIRAN, MABUHAY, ZAMBOANGA SIBUGAY | On-Going | ₱3.0M |
| 25JI0077 | Jul 11, 2025 | COMPLETION OF MULTI PURPOSE BUILDING, CATIPAN, MABUHAY, ZAMBOANGA SIBUGAY | On-Going | ₱3.0M |
| 25JI0078 | Jul 11, 2025 | COMPLETION OF MULTI PURPOSE BUILDING, PUNAWAN, MABUHAY, ZAMBOANGA SIBUGAY | Completed | ₱3.0M |
| 25JI0027 | Mar 24, 2025 | CONSTRUCTION OF MABUHAY COASTAL ROAD, ZAMBOANGA SIBUGAY | On-Going | ₱129.7M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.