Project 18K00218
DPWH infrastructure contract
Contract ID:
18K00218
Fingerprint:
a8f15fc2744467…4102580d00 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Aug 29, 2018 (8 yrs 2 mo ago) · Target/actual end Sep 28, 2019
Description:
CLUSTER '14' CONSTRUCTION OF MISSING LINKS/NEW ROADS, MISAMIS ORIENTAL
Category:
GAA 2018 OO-1
Implementing office:
DPWH Region X · Region X
Contractor:
MAC BUILDERS CORP. (FORMERLY: MAC BUILDERS DEVELOPMENT CORPORATION) · DPWH contractor code 7249
Contract amount:
₱549,835,734.90 (₱549.8M)
Funding source:
Regular Infra - GAA 2018 OO-1
Budget year:
2018
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25KL0138 | Dec 11, 2025 | LGU HOSPITALS, MISAMIS ORIENTAL PROVINCIAL HOSPITAL CLAVERIA, MISAMIS ORIENTAL | On-Going | ₱14.0M |
| 25KL0149 | Oct 17, 2025 | CONSTRUCTION OF SCHOOL BUILDING, BULAHAN INTEGRATED SCHOOL, BARANGAY BULAHAN CLAVERIA, MISAMIS ORIENTAL | On-Going | ₱15.0M |
| 25K00335 | Jul 2, 2025 | INSTALLATION OF SOLAR STREET LIGHTING ALONG CLAVERIA TO VILLANUEVA, CLAVERIA - VILLANUEVA, MISAMIS ORIENTAL | On-Going | ₱187.5M |
| 25KL0122 | Jun 3, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (CLASSROOM BUILDING) UNIVERSITY OF SCIENCE AND TECHNOLOGY OF THE PHILIPPINES, BRGY. POBLACION, CLAVERIA, MISAMIS ORIENTAL (PHASE 3) | On-Going | ₱49.5M |
| 25KL0056 | May 27, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (APOSKAHOY NHS), BARANGAY APOSKAHOY, CLAVERIA, MISAMIS ORIENTAL | On-Going | ₱4.9M |
| 25K00203 | May 26, 2025 | CONST. OF MISSING LINKS/NEW ROADS ,MALAYBALAY-GINGOOG ROAD (GINGOOG CITY-KALHAAN, CLAVERIA-BULONAY-MALAYBALAY CITY), PACKAGE 32, MISAMIS ORIENTAL | On-Going | ₱47.7M |
| 25KL0080 | May 26, 2025 | CONSTRUCTION OF ROAD, BARANGAY PARMBUGAS, CLAVERIA, MISAMIS ORIENTAL | On-Going | ₱4.9M |
| 25KL0081 | May 26, 2025 | CONSTRUCTION OF ROAD, SITIO MIGBANDAY, BARANGAY POBLACION - SITIO MABINI, BARANGAY STA. CRUZ, CLAVERIA, MISAMIS ORIENTAL (PACKAGE 2) | Completed | ₱4.9M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.