Project 18LA0143
DPWH infrastructure contract
Contract ID:
18LA0143
Fingerprint:
e40bdb5e1a1996…685c97c478 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Apr 13, 2018 (8 yrs 7 mo ago) · Target/actual end Dec 17, 2018
Description:
CONSTRUCTION OF MULTI-PURPOSE BUILDING (PUBLIC MARKET) AT BRGY. POBLACION, MUNICIPALITY OF NEW BATAAN, COMPOSTELA VALLEY PROVINCE
Category:
Buildings and Facilities
Implementing office:
DPWH Davao de Oro 1st DEO · Region XI
Contractor:
R. SEMILLA CONSTRUCTION & MARKETING · DPWH contractor code 9263
Contract amount:
₱3,438,707.74 (₱3.4M)
Funding source:
Regular Infra - GAA 2018 LP
Budget year:
2018
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| d1ddecb4b437… | Mar 28, 2018 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - COMPOSTELA VALLEY | ₱3,438,707.74 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25LI0073 | Jul 21, 2025 | CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG AGUIBAWA RIVER LEADING TO AGUSAN RIVER, PHASE 2, BARANGAY BANTACAN, NEW BATAAN, DAVAO DE ORO | On-Going | ₱144.7M |
| 25LI0079 | Jul 21, 2025 | CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG CABANBANAN RIVER LEADING TO AGUSAN RIVER, BANTACAN TO SAN ROQUE, NEW BATAAN, DAVAO DE ORO | On-Going | ₱118.8M |
| 25LI0045 | Apr 11, 2025 | CONCRETING OF PUROK-12 TO PUROK-13, BRGY. CAMANLANGAN FMR, BRGY. CAMANLANGAN, NEW BATAAN, DAVAO DE ORO | On-Going | ₱19.8M |
| 25LI0004 | Apr 4, 2025 | PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY - NABUNTURAN - MARAGUSAN RD K1441+(-)443-K1443+897 | On-Going | ₱95.5M |
| 25LI0010 | Apr 4, 2025 | PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY - MONTEVISTA - COMPOSTELA - MATI BDRY. RD K1486+(-307) - K1488+514 -K1490+208 | On-Going | ₱96.5M |
| 25LI0037 | Apr 4, 2025 | ROAD WIDENING - NABUNTURAN - MARAGUSAN ROAD K 1453+061 - K1455+563 | On-Going | ₱93.6M |
| 25LI0038 | Mar 26, 2025 | REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - MONTEVISTA - COMPOSTELA - MATI BDRY RD 1457+280 - K1457+325 | On-Going | ₱40.0M |
| 25LI0039 | Mar 26, 2025 | REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - NABUNTURAN - MARAGUSAN RD K1457+170 - K1457+250 | On-Going | ₱47.8M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.