Project 18M00004
DPWH infrastructure contract
Contract ID:
18M00004
Fingerprint:
7fdc9bb0148a6d…81a22f544e Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jun 11, 2018 (8 yrs 5 mo ago) · Target/actual end Jul 26, 2019
Description:
ROAD WIDENING WITH ROAD UPGRADING (ASPHALT TO CONCRETE)-MAKILALA ALLAH VALLEY ROAD, K1622+319-K1626+340, MAKILALA, NORTH COTABATO
Category:
Roads
Implementing office:
DPWH Region XII · Region XII
Contractor:
FFJJ CONSTRUCTION · DPWH contractor code 16712
Contract amount:
₱130,734,805.42 (₱130.7M)
Funding source:
Regular Infra - GAA 2018 OO-1
Budget year:
2018
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 3000e103d6cf… | Mar 6, 2018 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - REGION XII | ₱121,365,345.53 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 26MI0065 | Jun 18, 2026 | ASPHALT OVERLAY ALONG MAKILALA-ALLAH VALLEY RD - K1629 + 976 - K1631 + 134 | On-Going | ₱78.2M |
| 26MI0067 | Jun 18, 2026 | ASPHALT OVERLAY ALONG MAKILALA-ALLAH VALLEY RD - K1631 + 134 - K1631 + 650 | On-Going | ₱55.1M |
| 26MI0049 | Jun 11, 2026 | BUAYAN-LEPAGA-GAUNAN ROAD IN SUPPORT OF THE CAVENDISH BANANA PROJECT - STA 3+859.6 - STA. 4+081.1, MLANG, COTABATO | Completed | ₱9.1M |
| 25MI0115 | Mar 30, 2026 | RAINWATER COLLECTOR SYSTEM | Completed | ₱2.6M |
| 25MI0112 | Mar 23, 2026 | (RE-BID) CONSTRUCTION OF SCHOOL BUILDING, DUNGO-AN HIGH SCHOOL, BRGY. DUNGO-AN, MLANG, COTABATO | On-Going | ₱19.9M |
| 25MI0093 | Aug 26, 2025 | CONSTRUCTION OF BRIDGE, LEADING TO THE BOUNDARY OF THE CENTRAL MINDANAO AIRPORT, BRGY. NEW RIZAL, MLANG, COTABATO | On-Going | ₱56.4M |
| 25MI0078 | Aug 19, 2025 | KIDAPAWAN-CALUNASAN-MLANG RD - K1634+775-K1634+900 | Completed | ₱29.2M |
| 25MI0091 | Aug 19, 2025 | COMPLETION/REHABILITATION OF MULTI-PURPOSE BUILDING (COVERED COURT) IN BRGY. NEW ANTIQUE, MLANG, COTABATO | On-Going | ₱4.7M |