Project 18MF0020
DPWH infrastructure contract
Contract ID:
18MF0020
Fingerprint:
d049a6279aed7e…ba4f8268a7 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 8, 2018 (8 yrs 8 mo ago) · Target/actual end Nov 27, 2018
Description:
CONSTRUCTION OF BARANGAY HALL AT BRGY. ESTRELLA, PRES. QUIRINO, SULTAN KUDARAT.
Category:
Buildings and Facilities
Implementing office:
DPWH Sultan Kudarat 1st DEO · Region XII
Contractor:
DALANON CONSTRUCTION CORPORATION (FORMERLY:DALANON CONSTRUCTION REF. SUPPLY & SERVICE) · DPWH contractor code 11205
Contract amount:
₱2,569,135.20 (₱2.6M)
Funding source:
Regular Infra - GAA 2018 LP
Budget year:
2018
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25MG0020 | Apr 11, 2025 | ROAD WIDENING-MIDSAYAP-MARBEL RD-K1774+083-K1774+581 | Completed | ₱9.6M |
| 25MF0031 | Mar 26, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (BARANGAY HALL), BARANGAY BANNAWAG, PRESIDENT QUIRINO, SULTAN KUDARAT | Completed | ₱3.0M |
| 25MF0032 | Mar 26, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (MINI GYM BLEACHERS), BARANGAY BANNAWAG, PRESIDENT QUIRINO, SULTAN KUDARAT | Completed | ₱3.0M |
| 25MG0002 | Feb 28, 2025 | PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY-MIDSAYAP-MARBEL RD-K1774+083-K1774+336, SOUH COTABATO | Completed | ₱11.2M |
| 25MG0003 | Feb 28, 2025 | PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY-MIDSAYAP-MARBEL RD-K1775+000-K1775+570, SOUTH COTABATO | Completed | ₱38.0M |
| 24M00200 | Jul 29, 2024 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY POBLACION, PRESIDENT QUIRINO, SULTAN KUDARAT | Completed | ₱9.9M |
| 24MF0052 | May 15, 2024 | CONSTRUCTION OF 1-STOREY 2-CLASSROOM SCHOOL BUILDING IN PRESIDENT QUIRINO NATIONAL HIGH SCHOOL, BARANGAY POBLACION, PRESIDENT QUIRINO, SULTAN KUDARAT | Completed | ₱5.0M |
| 24MG0050 | May 15, 2024 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. NEW CUYAPO, TANTANGAN, SOUTH COTABATO | Completed | ₱4.9M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.