PisoScan

Project 18MF0098

DPWH infrastructure contract
Contract ID:
18MF0098
Fingerprint:
d7318f055db8a0…04affc1b71 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jul 30, 2018 (8 yrs 3 mo ago) · Target/actual end Jun 4, 2019
Description:
CONST. OF 3-STY 6-CLASSROOMS LABORATORY BUILDING AT APOLINARIO S. BERNARDO NHS, TACURONG CITY, SULTAN KUDARAT.
Category:
Buildings and Facilities
Implementing office:
Contractor:
BRE CONSTRUCTION · DPWH contractor code 32605
Contract amount:
₱35,532,599.28 (₱35.5M)
Funding source:
Outside Infra - GAA 2018 DepEd BEFF
Budget year:
2018

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
f0b3d83d0682…Jul 13, 2018DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - SULTAN KUDARAT DEO₱35,532,599.28

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25M00262Aug 11, 2025PREVENTIVE MAINTENANCE - DULAWAN-MARBEL RD - K1768 + 571 - K1769 + 071, TACURONG, SULTAN KUDARATOn-Going₱46.8M
25MF0036Jul 28, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. RAJAH MUDA, TACURONG, SULTAN KUDARATCompleted₱4.8M
25MF0037Jul 28, 2025CONSTRUCTION OF RIVERWALL PROTECTION PROJECTS IN BRGY. RAJAH NUDA AND BRGY. PARAS, TACURONG, SULTAN KUDARATCompleted₱4.8M
25MF0003Mar 26, 2025PREVENTIVE MAINTENANCE OF ROAD:ASPHALT OVERLAY - DULAWAN - MARBEL RD - K1764 + (-526) - K1764 + 344Completed₱98.4M
25MF0004Mar 26, 2025PREVENTIVE MAINTENANCE OF ROAD:ASPHALT OVERLAY - DULAWAN - MARBEL RD - K1762 + 433 - K1763 + 418Completed₱110.0M
25MF0005Mar 26, 2025CONSTRUCTION OF DRAINAGE STRUCTURE ALONG ROAD - KIDAPAWAN - ALLAH JUNCTION ROAD K1674 + 056 - K1674 + 719Completed₱20.8M
25MF0007Mar 26, 2025ROAD WIDENING - DULAWAN - MARBEL ROAD - K1758 + 524 - K1760 + 404On-Going₱53.4M
25MF0008Mar 26, 2025ROAD WIDENING - DULAWAN - MARBEL RD - K1766 + 064 - K1766 + 640Completed₱17.1M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.