FY2026 GAA: ₱6.79T
PisoScan

Project 18NG0114

DPWH infrastructure contract
Contract ID:
18NG0114
Fingerprint:
e402781bea40d8…27ae95cde9 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Sep 23, 2018 (8 yrs 1 mo ago) · Target/actual end Jul 16, 2020
Description:
CONSTRUCTION OF 1 STY 3 UNITS REGULAR WORKSHOP, 2 UNITS SCIENCE LAB & 2 UNITS ICT (7MX18M PER UNIT), GEN. LUNA NATIONAL HIGH SCHOOL (304777) GEN. LUNA, SURIGAO DEL NORTE
Category:
Buildings and Facilities
Implementing office:
Contractor:
INMAR BUILDER AND ENTERPRISES · DPWH contractor code 38128
Contract amount:
₱29,823,343.36 (₱29.8M)
Funding source:
Outside Infra - GAA 2018 DepEd BEFF
Budget year:
2018

Matching PhilGEPS award entries (same contractor, same contract ID)

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25NF0102Nov 25, 2025CONSTRUCTION OF FLOOD CONTROL - DRAINAGE SYSTEM, GENERAL LUNA, SURIGAO DEL NORTEOn-Going₱57.8M
25NF0093Sep 4, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING (HALF-WAY HOUSE), GENERAL LUNA, SURIGAO DEL NORTECompleted₱9.9M
25NF0061Jul 18, 2025CONSTRUCTION / INSTALLATION OF SOLAR LIGHTS WITH SAFETY SIGNS AND DEVICES, GENERAL LUNA - CATANGNAN (CLOUD 9), GENERAL LUNA, SURIGAO DEL NORTEOn-Going₱93.6M
25NF0073Jul 18, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY STA. FE, GENERAL LUNA, SURIGAO DEL NORTECompleted₱4.9M
25NF0051Mar 28, 2025CONSTRUCTION OF DRAINAGE STRUCTURE, BARANGAY POBLACION, GENERAL LUNA, SURIGAO DEL NORTEOn-Going₱54.0M
25NF0039Mar 25, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING (BARANGAY HALL), BARANGAY POBLACION 2, GENERAL LUNA, SURIGAO DEL NORTECompleted₱4.9M
25NF0043Mar 25, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING (BARANGAY HALL), BARANGAY CONSUELO, GENERAL LUNA, SURIGAO DEL NORTECompleted₱4.9M
25NF0006Feb 24, 2025CONSTRUCTION OF ROAD, BARANGAY SANTA FE, GENERAL LUNA, SURIGAO DEL NORTEOn-Going₱9.8M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.