FY2026 GAA: ₱6.79T
PisoScan

Project 18OI0073

DPWH infrastructure contract
Contract ID:
18OI0073
Fingerprint:
8c56a2955d04d5…3c63a69f4e Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jun 29, 2018 (8 yrs 4 mo ago) · Target/actual end Jun 23, 2019
Description:
CONSTRUCTION OF SLOPE PROTECTION INCLUDING BOX CULVERT AND REMOVAL OF INFORMAL SETTLERS ALONG LAS PI
Category:
Flood Control: Construction - Drainage (e.g., Closed and Open Conduits, Spillway), Roads: Construction - PCCP
Implementing office:
DPWH Las Piñas-Muntinlupa DEO · National Capital Region
Contractor:
Contract amount:
₱120,765,097.61 (₱120.8M)
Funding source:
Regular Infra - Flood Control: Construction - Drainage (e.g., Closed and Open Conduits, Spillway), Roads: Construction - PCCP
Budget year:
2018

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25OC0132Jul 15, 2025REHABILITATION OF C-5 EXTENSION ROAD IN PARAÑAQUE CITY, PARAÑAQUE CITY, METRO MANILAOn-Going₱27.2M
25OI0116Jun 20, 2025COMPLETION OF MULTI-PURPOSE BUILDING AT BARANGAY ZAPOTE, LAS PINAS CITYOn-Going₱3.9M
25OI0117Jun 20, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BARANGAY TALON 4, LAS PINAS CITYOn-Going₱11.6M
25OI0058Jun 13, 2025COMPLETION OF MULTI PURPOSE BLDG., CAA, LAS PINAS CITY LONE DISTRICOn-Going₱4.9M
25OI0059Jun 13, 2025REHABILITATION OF ROAD INCLUDING DRAINAGE, ILAYA, LAS PINAS CITY LONE DISTRICTOn-Going₱4.9M
25OI0061Jun 13, 2025CONSTRUCTION OF MULTI-PURPOSE BLDG., TALON 2, LAS PINAS CITY LONE DISTRICT PHASE 2.Completed₱7.8M
25OI0062Jun 13, 2025REHABILITATION OF MULTI-PURPOSE BLDG., TALON 4, LAS PINAS CITY LONE DISTRICTOn-Going₱7.8M
25OI0063Jun 13, 2025REHABILITATION OF ROAD INCLUDING DRAINAGE, PAMPLONA 3, LAS PINAS CITY LONE DISTRICTOn-Going₱17.5M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.